DMD-2026-003
Medium-term plan implementation tracker
- Priority score
- 82
- Estimated cost
- SYP 700M
- Net present value
- SYP 391.2M
- Internal rate of return
- 23.4%
- Payback period
- 3.3 years
- Rank in the 2027 plan
- —
Score confirmed by the evaluation panel
- Gate into «Submitted»DecisionGoDate19 January 2026DraftComplete
- Gate into «Initial review»DecisionGoDate18 February 2026SubmittedComplete
- Gate into «Feasibility»DecisionGoDate21 March 2026Initial reviewComplete
- Gate into «Evaluation»DecisionGoDate20 April 2026FeasibilityComplete
- Gate into «Committee review»DecisionGoDate21 May 2026EvaluationComplete
- Gate into «Approved»DecisionGoDate20 June 2026Committee reviewComplete
- Gate into «Prioritized»DecisionGoDate21 July 2026ApprovedComplete
- Gate into «Converted to project»DecisionGoDate20 August 2026PrioritizedComplete
- Converted to projectCurrent stageCurrent stage
Priority class
Top priority
Computed from the score and the approved model’s thresholds; may be changed with a reason kept in the history
By the model: P1 (score 82)
Class thresholds
The approved model (version 4) with the eleven criteria; the score is the weighted mean of the ratings scaled to 100.
Evaluation against the priority model
| Criterion | Weight | Rating (1–5) | Contribution |
|---|---|---|---|
| Value | |||
| Fit with the development frameworkHow far the proposal moves the objectives of the 2026–2030 development framework, its six pillars and the initiatives and KPIs of the 2026–2028 medium-term plan.Raises priority | 20% | 5.0 | 20.0 |
| Development valueThe value it adds for citizens and the governorates: a public service restored, infrastructure rehabilitated or a new national capability.Raises priority | 12% | 5.0 | 12.0 |
| Economic & social returnThe economic and social return in the feasibility study, and its contribution to rationalised investment spending and restored production.Raises priority | 8% | 5.0 | 8.0 |
| Urgency & compliance | |||
| UrgencyThe cost of delay: what citizens and the beneficiary bodies lose if work does not start this year.Raises priority | 10% | 4.8 | 9.5 |
| Legal requirementIs it required by a law, a decree, a Council of Ministers decision or a directive from a control body or the competent ministry (Ministry of Communications and IT, the Central Organisation for Financial Control)?Raises priority | 10% | 1.4 | 1.0 |
| Impact | |||
| Impact on citizens & beneficiariesIts direct effect on citizens, returning families, students, patients and farmers: time, effort, cost and satisfaction.Raises priority | 14% | 3.9 | 10.2 |
| Sustainability impactIts contribution to energy and water efficiency in public facilities, renewable energy and lower emissions.Raises priority | 3% | 1.8 | 0.6 |
| Digital transformation impactIts contribution to digital government services, public-body processes and the use of statistical data.Raises priority | 5% | 5.0 | 5.0 |
| Effort & risk | |||
| RiskDelivery, technical and contractual risk — the higher it is, the lower the priority.Lowers priority | 7% | 1.3 | 6.5 |
| ComplexityThe number of bodies, governorates, systems, integrations and procedure changes involved.Lowers priority | 6% | 2.2 | 4.2 |
| Resource requirementThe team, budget and scarce skills it draws from the portfolio’s capacity.Lowers priority | 5% | 1.3 | 4.6 |
| Priority scoreScore confirmed by the evaluation panel | 82 / 100 | ||
Evaluation profile
This request’s ratings against the average approved request
- This request
- Approved average
| Category | This request | Approved average |
|---|---|---|
| Alignment | 100 | 94 |
| Value | 100 | 91 |
| Return | 100 | 77 |
| Urgency | 95 | 79 |
| Regulatory | 10 | 27 |
| Risk | 93 | 89 |
| Complexity | 70 | 79 |
| Resources | 93 | 91 |
| Beneficiary | 73 | 63 |
| Sustainability | 20 | 30 |
| Digital | 100 | 58 |
Evaluation panel
The request goes to committee only when everyone has signed
Kinan Azzam
Senior Digital Delivery Consultant — National PMO
Technical evaluation complete
Signed 2026-05-21Huda Al-Dandal
Senior Financial Analyst — Investment Plan
Financial review complete
Signed 2026-05-21Eng. Rita Ghanem
Enterprise Architect
Architecture review complete
Signed 2026-05-21