PRJ-2026-021On track3PlanningConstructionNot startedDelivered by:Ministry of Transport

Deir ez-Zor Suspension Bridge Reconstruction

Add to watchlist

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

Budget (BAC)

SYP 13B

Actual cost

SYP 260M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 13B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
1On track
4At risk
0Late
Average delay58 days
Oct 26Jan 27Apr 27Jul 27Oct 27Jan 28Apr 28Jul 28Oct 28Jan 29
Contractual
Build completePlanned: ⁦2027-11-30⁩Forecast / actual: ⁦2028-01-27⁩Delay: 58 daysG3 +58
Executive
Project plan approvedPlanned: ⁦2026-10-29⁩Forecast / actual: ⁦2027-02-16⁩Delay: 110 daysG1 +110
Payment
Final handoverPlanned: ⁦2028-12-31⁩Forecast / actual: ⁦2029-01-06⁩Delay: 6 daysG5 +6
Regulatory
Testing & acceptance completePlanned: ⁦2028-07-25⁩Forecast / actual: ⁦2028-08-21⁩Delay: 27 daysG4 +27
Project
Designs approvedPlanned: ⁦2027-04-05⁩Forecast / actual: ⁦2027-07-04⁩Delay: 90 daysG2 +90

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-10-29⁩⁦2027-02-16⁩⁦+110⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAt risk0Not requested
Designs approvedMS-G2Project⁦2027-04-05⁩⁦2027-07-04⁩⁦+90⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAt risk0Not requested
Build completeMS-G3Contractual⁦2027-11-30⁩⁦2028-01-27⁩⁦+58⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2028-07-25⁩⁦2028-08-21⁩⁦+27⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAt risk0Not requested
Final handoverMS-G5Payment⁦2028-12-31⁩⁦2029-01-06⁩⁦+6⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦2%⁩

Awaiting acceptance

⁦0%⁩

Not handed in

⁦98%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline021-D1⁦2%⁩CRT-021-01ApprovedEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syEng. Wassim Al-Azm⁦2026-08-10⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting021-D2⁦3%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-10-29⁩V0⁦0⁩ of ⁦3⁩
Detailed design021-D3⁦6%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2027-01-16⁩V0⁦0⁩ of ⁦3⁩
Permits & approvals021-D4⁦6%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2027-04-05⁩V0⁦0⁩ of ⁦3⁩
Site works & excavation021-D5⁦13%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2027-06-24⁩V0⁦0⁩ of ⁦3⁩
Structure021-D6⁦13%⁩—DraftEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syEng. Wassim Al-Azm⁦2027-09-11⁩V0⁦0⁩ of ⁦3⁩
Finishes021-D7⁦13%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2027-11-30⁩V0⁦0⁩ of ⁦3⁩
Supply021-D8⁦10%⁩—DraftEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syEng. Wassim Al-Azm⁦2028-02-17⁩V0⁦0⁩ of ⁦3⁩
Installation021-D9⁦10%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2028-05-07⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning021-D10⁦10%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2028-07-25⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance021-D11⁦7%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2028-10-13⁩V0⁦0⁩ of ⁦3⁩
Final acceptance021-D12⁦7%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2028-12-31⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩