Deir ez-Zor Suspension Bridge Reconstruction
Add to watchlistRebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution12 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-10-29 | 2027-02-16 | +110 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-04-05 | 2027-07-04 | +90 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-11-30 | 2028-01-27 | +58 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2028-07-25 | 2028-08-21 | +27 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-12-31 | 2029-01-06 | +6 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
2%Awaiting acceptance
0%Not handed in
98%Deliverable flow
Display options
| Project plan & baseline021-D1 | 2% | CRT-021-01 | Approved | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Eng. Wassim Al-Azm | 2026-08-10 | V1 | 3 of 3 |
| Monitoring & reporting021-D2 | 3% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-10-29 | V0 | 0 of 3 |
| Detailed design021-D3 | 6% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-01-16 | V0 | 0 of 3 |
| Permits & approvals021-D4 | 6% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2027-04-05 | V0 | 0 of 3 |
| Site works & excavation021-D5 | 13% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2027-06-24 | V0 | 0 of 3 |
| Structure021-D6 | 13% | — | Draft | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Eng. Wassim Al-Azm | 2027-09-11 | V0 | 0 of 3 |
| Finishes021-D7 | 13% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-11-30 | V0 | 0 of 3 |
| Supply021-D8 | 10% | — | Draft | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Eng. Wassim Al-Azm | 2028-02-17 | V0 | 0 of 3 |
| Installation021-D9 | 10% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2028-05-07 | V0 | 0 of 3 |
| Testing & commissioning021-D10 | 10% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2028-07-25 | V0 | 0 of 3 |
| Provisional acceptance021-D11 | 7% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2028-10-13 | V0 | 0 of 3 |
| Final acceptance021-D12 | 7% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2028-12-31 | V0 | 0 of 3 |
| Total · 12 | 100% |