PRJ-2026-021On track3PlanningConstructionNot startedDelivered by:Ministry of Transport

Deir ez-Zor Suspension Bridge Reconstruction

Add to watchlist

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

Budget (BAC)

SYP 13B

Actual cost

SYP 260M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 13B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-09-07⁩
ApprovedDMD-2026-021Deir ez-Zor Suspension Bridge Reconstruction

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-021
Project
Deir ez-Zor Suspension Bridge Reconstruction
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Wael Al-Khawlani

1The proposalAuto-filled

TitleAuto-filled
Deir ez-Zor Suspension Bridge Reconstruction
Proposed byAuto-filled
Eng. Wael Al-Khawlani
DepartmentAuto-filled
Transport & Housing Projects Directorate
Submitted onAuto-filled
⁦2025-09-07⁩
Proposal numberAuto-filled
DMD-2026-021

2Justification

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

3Objectives

  1. Rebuild damaged areas and provide replacement housing
  2. Rehabilitate core energy, water and transport infrastructure

Strategic objectives served

  • SO-2.2 — Rebuild damaged areas and provide replacement housing
  • SO-2.1 — Rehabilitate core energy, water and transport infrastructure

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SYP 13B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 9.4B
Supervision & consultingSYP 1.8B
Internal teamSYP 1.2B
Contingency reserve (5%)SYP 650M
TotalSYP 13B

6Initial risks

RiskLevelProposed response
Bids 18% above the engineering estimateHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsSubmitted—⁦2025-09-07⁩ 11:38
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2025-09-08⁩ 09:18
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-09-10⁩ 10:25
4Portfolio manager reviewTechnical acceptanceEng. Wassim Al-AzmPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-09-15⁩ 11:32
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-09-18⁩ 11:14
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2025-09-24⁩ 13:46

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2025-09-08⁩

PMO review

Mariam Al-Zoubi

Approved⁦2025-09-10⁩

Portfolio manager review

Eng. Wassim Al-Azm

Approved⁦2025-09-15⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2025-09-18⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2025-09-24⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Wael Al-Khawlani on ⁦2025-09-07⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2025-09-08⁩ at ⁦09:18⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-09-10⁩ at ⁦10:25⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Wassim Al-Azm · Portfolio manager

    Approved · ⁦2025-09-15⁩ at ⁦11:32⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-18⁩ at ⁦11:14⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2025-09-24⁩ at ⁦13:46⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-09-28⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Wael Al-Khawlani

  2. V1Returned for edit⁦2025-09-07⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Wael Al-Khawlani

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close