PRJ-2026-018At risk4ExecutionConstructionIn progressDelivered by:Ministry of Communications and Information Technology

Government Fibre Backbone — Damascus–Homs Segment

Add to watchlist

Laying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.3B

Actual cost

SYP 1.9B

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 3.4B

+SYP 102.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
PSA-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
ApprovedPRJ-2026-018Government Fibre Backbone — Damascus–Homs Segment

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-018
Project
Government Fibre Backbone — Damascus–Homs Segment
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. George Haddad

1Weight and relative weightAuto-filled

Project weight score

62 of 100

Relative weight in the portfolio

⁦11.3%⁩

Portfolio

Reconstruction & Infrastructure Portfolio

8 projects

Its share of the portfolio’s progress

6.2 points of 35.3%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩321.0
Budget sizeApproved budget (BAC)⁦25%⁩315.0
Impact on citizens & beneficiariesThe project’s alignment score⁦20%⁩416.0
Complexity & riskThe project’s risk score⁦10%⁩36.0
Project classificationThe project’s classification⁦10%⁩24.0
Weight score—⁦100%⁩—62

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
Darayya Replacement Housing100⁦18.3%⁩⁦42%⁩
Deir ez-Zor Suspension Bridge Reconstruction89⁦16.3%⁩⁦2%⁩
Douma Wastewater Treatment Plant88⁦16.1%⁩⁦44%⁩
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate80⁦14.6%⁩⁦33%⁩
Population & Housing Census Preparation — Phase 166⁦12.1%⁩⁦2%⁩
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals62⁦11.3%⁩⁦79%⁩
Government Fibre Backbone — Damascus–Homs Segment62⁦11.3%⁩⁦55%⁩
Unified Government Contact Centre & AI Assistant69Not counted⁦0%⁩
Weighted portfolio progress—⁦100%⁩⁦35.3%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2026-09-16⁩ 11:32
2Weight model complianceMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-09-17⁩ 13:16
3Portfolio manager approvalTechnical acceptanceEng. Wassim Al-AzmPortfolio managerApproved—⁦2026-09-22⁩ 14:23

Signatures

Weight model compliance

Mariam Al-Zoubi

Approved⁦2026-09-17⁩

Portfolio manager approval

Eng. Wassim Al-Azm

Approved⁦2026-09-22⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-09-17⁩ at ⁦13:16⁩

  2. Technical acceptance

    Portfolio manager approval

    Eng. Wassim Al-Azm · Portfolio manager

    Approved · ⁦2026-09-22⁩ at ⁦14:23⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Reem Al-Qabbani

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity

    Dr. Reem Al-Qabbani

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close