Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-018At risk4ExecutionConstructionIn progressDelivered by:Ministry of Communications and Information Technology

Government Fibre Backbone — Damascus–Homs Segment

Add to watchlist

Laying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.3B

Actual cost

SYP 1.9B

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 3.4B

+SYP 102.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
PSA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2024-12-07⁩
ApprovedPRJ-2026-018Government Fibre Backbone — Damascus–Homs Segment

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-018
Project
Government Fibre Backbone — Damascus–Homs Segment
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. George Haddad

1The resultAuto-filled

Priority score

71 of 100

Class

P2

60–74

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the development framework⁦20%⁩5.020.0
Development value⁦12%⁩4.711.1
Economic & social return⁦8%⁩4.36.6
Urgency⁦10%⁩3.97.3
Legal requirement⁦10%⁩1.61.5
Risk⁦7%⁩2.24.9
Complexity⁦6%⁩2.43.9
Resource requirement⁦5%⁩2.03.8
Impact on citizens & beneficiaries⁦14%⁩3.58.8
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩2.62.0
Total⁦100%⁩—71

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2024-12-07⁩ 12:15
2Evaluation checked against the modelMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-12-09⁩ 10:49
3Portfolio manager reviewTechnical acceptanceEng. Wassim Al-AzmPortfolio managerApproved—⁦2024-12-10⁩ 11:56
4Class approved — Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2024-12-16⁩ 08:00
5Class approved — Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2024-12-17⁩ 12:03

Signatures

Evaluation checked against the model

Mariam Al-Zoubi

Approved⁦2024-12-09⁩

Portfolio manager review

Eng. Wassim Al-Azm

Approved⁦2024-12-10⁩

Class approved — Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2024-12-17⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2024-12-07⁩

  1. Methodology review

    Evaluation checked against the model

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-12-09⁩ at ⁦10:49⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Wassim Al-Azm · Portfolio manager

    Approved · ⁦2024-12-10⁩ at ⁦11:56⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2024-12-17⁩ at ⁦12:03⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2024-12-07⁩

    Evaluated on the approved priority model

    Mariam Al-Zoubi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close