Ministry of Finance e-Archiving
Add to watchlistElectronic archiving of the Ministry of Finance’s documents and financial correspondence, with a workflow for administrative correspondence and one search across the archive.
Budget (BAC)
Actual cost
95% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
46 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-07 | 2025-06-27 | +20 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-09-21 | 2025-10-27 | +36 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-01 | 2026-04-28 | +58 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-06-15 | 2026-08-28 | +74 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-09-30 | 2026-12-24 | +85 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Late | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
95%Awaiting acceptance
5%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline017-D1 | 4% | CRT-017-01 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Rasha Al-Mudarres | 2025-04-14 | V1 | 3 of 3 |
| Monitoring & reporting017-D2 | 4% | CRT-017-02 | Approved | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2025-06-07 | V1 | 3 of 3 |
| Business requirements017-D3 | 9% | CRT-017-03 | Approved | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2025-07-30 | V1 | 3 of 3 |
| Solution design017-D4 | 9% | CRT-017-04 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Rasha Al-Mudarres | 2025-09-21 | V1 | 3 of 3 |
| Release 1017-D5 | 14% | CRT-017-05 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Rasha Al-Mudarres | 2025-11-14 | V1 | 3 of 3 |
| Release 2017-D6 | 14% | CRT-017-06 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Rasha Al-Mudarres | 2026-01-06 | V1 | 3 of 3 |
| Integrations017-D7 | 13% | CRT-017-07 | Approved | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2026-03-01 | V1 | 3 of 3 |
| System testing017-D8 | 10% | CRT-017-08 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Rasha Al-Mudarres | 2026-04-23 | V1 | 3 of 3 |
| User acceptance testing017-D9 | 10% | CRT-017-09 | Approved | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2026-06-15 | V1 | 3 of 3 |
| Training & change017-D10 | 8% | CRT-017-10 | Approved | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2026-08-08 | V1 | 3 of 3 |
| Go-live & handover017-D11 | 5% | — | Submitted | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Rasha Al-Mudarres | 2026-09-30 | V1 | 1 of 3 |
| Total · 11 | 100% |