Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-017At risk5ClosureWaterfallIn progressDelivered by:Ministry of Finance

Ministry of Finance e-Archiving

Add to watchlist

Electronic archiving of the Ministry of Finance’s documents and financial correspondence, with a workflow for administrative correspondence and one search across the archive.

Budget (BAC)

SYP 355M

Actual cost

SYP 337.3M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 355M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-02-26⁩
ApprovedCRT-017-06Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Ministry of Finance e-Archiving
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Salma Al-Zaim
Project manager
Nour Al-Jabiri

1The deliverableAuto-filled

DeliverableAuto-filled
Release 2
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Nour Al-Jabiri
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦14%⁩
DueAuto-filled
⁦2026-01-06⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-017_3.2_v1.pdfV1Nour Al-Jabiri⁦2025-11-20⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Rasha Al-Mudarres
Accepted byAuto-filled
Salma Al-Zaim
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2025-019
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Nour Al-JabiriDirector, Government Systems & IntegrationSubmitted—⁦2025-11-20⁩ 11:44
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-11-23⁩ 13:04
3Inspection & technical acceptance — ownerTechnical acceptanceSalma Al-ZaimProject ownerOn behalf of Rasha Al-MudarresApprovedInspected and accepted against the approved acceptance criteria.⁦2025-11-26⁩ 14:11
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-11-30⁩ 12:39
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-12-01⁩ 13:16

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2025-11-23⁩

Inspection & technical acceptance — owner

Salma Al-Zaim

Approved⁦2025-11-26⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2025-11-30⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2025-12-01⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Nour Al-Jabiri on ⁦2025-11-20⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-11-23⁩ at ⁦13:04⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Rasha Al-Mudarres · Project owner

    Approved · ⁦2025-11-26⁩ at ⁦14:11⁩ · On behalf of Rasha Al-Mudarres (Salma Al-Zaim)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-11-30⁩ at ⁦12:39⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-12-01⁩ at ⁦13:16⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-11-20⁩

    PRJ-2026-017_3.2_v1.pdf

    Nour Al-Jabiri

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close