PRJ-2026-005On track4ExecutionWaterfallIn progressDelivered by:Ministry of Communications and Information Technology

Government Network Cybersecurity Programme

Add to watchlist

A round-the-clock security operations centre, identity and access protection, penetration testing and higher compliance of government bodies with the national cybersecurity controls.

Budget (BAC)

SYP 965M

Actual cost

SYP 824.5M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SYP 936.9M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
PSA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-02-09⁩
ApprovedMTG-KO-005Kick-off — Government Network Cybersecurity Programme

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-005
Project
Government Network Cybersecurity Programme
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. Hussam Zeidan

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Government Network Cybersecurity Programme
Date and timeAuto-filled
⁦2025-02-09⁩ · 10:00
PlaceAuto-filled
Main meeting room — Authority HQ, Kafr Sousa
SecretaryAuto-filled
Eng. Hussam Zeidan

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Khaled Al-KayyaliDeputy President, Digital Transformation
Eng. Mazen KassabDirector General, Government Digital Infrastructure
Eng. Hussam ZeidanDirector, Cybersecurity
Dr. Reem Al-QabbaniDirector, National Project Management Office
Eng. Dima Al-DabbaghMunjaz Platform Administrator

2Roles

PersonRoleDuty
Eng. Khaled Al-KayyaliProject sponsorSponsors the project, decides escalations and material changes
Eng. Mazen KassabProject ownerApproves the requirements and accepts the deliverables
Eng. Hussam ZeidanProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Reem Al-QabbaniProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Dima Al-DabbaghPlatform engineer, cybersecurity programmeDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. Hussam Zeidan⁦2025-07-05⁩Done
Designs approvedEng. Hussam Zeidan⁦2025-10-30⁩Done
Build completeEng. Hussam Zeidan⁦2026-04-24⁩Done
Testing & acceptance completeEng. Hussam Zeidan⁦2026-08-20⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. Project Approval Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-05-22⁩
Start confirmed
Eng. Khaled Al-Kayyali · ⁦2025-02-10⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Hussam ZeidanDirector, CybersecuritySubmitted—⁦2025-02-10⁩ 10:49
2Chair’s approval (sponsor)Technical acceptanceEng. Khaled Al-KayyaliProject sponsorApproved—⁦2025-02-11⁩ 12:30
3Minutes against the templateMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-02-12⁩ 14:23

Signatures

Minutes against the template

Mariam Al-Zoubi

Approved⁦2025-02-12⁩

Chair’s approval (sponsor)

Eng. Khaled Al-Kayyali

Approved⁦2025-02-11⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Hussam Zeidan on ⁦2025-02-10⁩

  1. Methodology review

    Minutes against the template

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-02-12⁩ at ⁦14:23⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Khaled Al-Kayyali · Project sponsor

    Approved · ⁦2025-02-11⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-02-09⁩

    The minutes as taken

    Eng. Hussam Zeidan

Only one version so far.