Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-003At risk4ExecutionWaterfallIn progressDelivered by:Ministry of Communications and Information Technology

Government Backup Data Centre, Homs — Phase 2

Add to watchlist

A Tier III standby site in Homs, away from the capital, that keeps the government e-services platform and the ministries’ systems running after a major outage at the main Damascus data centre.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.7B

Actual cost

SYP 2.9B

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SYP 4.1B

+SYP 365.9M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+40⁩ days vs approved

Baseline (original = approved)⁦2026-11-30⁩
Current forecast⁦2027-01-09⁩
By earned schedule⁦2027-09-03⁩
Critical activities
5
of ⁦6⁩ open activities
Late activities
4
past their baseline finish
Schedule performance
0.73
earned ÷ planned value
Next milestone
in 41 days
Testing & acceptance complete
Expand allCollapse all
Activity
Government Backup Data Centre, Homs — Phase 2Planned: ⁦2025-04-06⁩ → ⁦2026-11-30⁩Forecast: ⁦2025-04-06⁩ → ⁦2027-01-09⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-04-06⁩ → ⁦2025-08-19⁩Actual: ⁦2025-04-06⁩ → ⁦2025-10-18⁩
Project plan & baselinePlanned: ⁦2025-04-06⁩ → ⁦2025-06-28⁩Actual: ⁦2025-04-06⁩ → ⁦2025-08-04⁩
Monitoring & reportingPlanned: ⁦2025-05-28⁩ → ⁦2025-08-19⁩Actual: ⁦2025-06-20⁩ → ⁦2025-10-18⁩
Project plan approvedPlanned: ⁦2025-08-19⁩ → ⁦2025-08-19⁩Actual: ⁦2025-10-18⁩ → ⁦2025-10-18⁩Project plan approved
Analysis & designPlanned: ⁦2025-07-19⁩ → ⁦2025-12-01⁩Actual: ⁦2025-09-03⁩ → ⁦2026-03-17⁩
Business requirementsPlanned: ⁦2025-07-19⁩ → ⁦2025-10-10⁩Actual: ⁦2025-09-03⁩ → ⁦2026-01-01⁩
Solution designPlanned: ⁦2025-09-09⁩ → ⁦2025-12-01⁩Actual: ⁦2025-11-17⁩ → ⁦2026-03-17⁩
Designs approvedPlanned: ⁦2025-12-01⁩ → ⁦2025-12-01⁩Actual: ⁦2026-03-17⁩ → ⁦2026-03-17⁩Designs approved
BuildPlanned: ⁦2025-10-31⁩ → ⁦2026-05-06⁩Actual: ⁦2026-01-31⁩ → ⁦2026-10-26⁩
Release 1Planned: ⁦2025-10-31⁩ → ⁦2026-01-22⁩Actual: ⁦2026-01-31⁩ → ⁦2026-05-31⁩
Release 2Planned: ⁦2025-12-22⁩ → ⁦2026-03-15⁩Actual: ⁦2026-04-16⁩ → ⁦2026-08-14⁩
IntegrationsPlanned: ⁦2026-02-12⁩ → ⁦2026-05-06⁩Actual: ⁦2026-06-30⁩ → ⁦2026-10-26⁩
Build completePlanned: ⁦2026-05-06⁩ → ⁦2026-05-06⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Build complete
Testing & acceptancePlanned: ⁦2026-04-05⁩ → ⁦2026-08-18⁩Forecast: ⁦2026-04-05⁩ → ⁦2026-12-08⁩Float: ⁦0⁩d
System testingPlanned: ⁦2026-04-05⁩ → ⁦2026-06-27⁩Forecast: ⁦2026-04-05⁩ → ⁦2026-11-22⁩Float: ⁦0⁩dDrag to change its duration+148
User acceptance testingPlanned: ⁦2026-05-27⁩ → ⁦2026-08-18⁩Forecast: ⁦2026-11-13⁩ → ⁦2026-12-08⁩Float: ⁦0⁩dDrag to change its dates+112
Testing & acceptance completePlanned: ⁦2026-08-18⁩ → ⁦2026-08-18⁩Forecast: ⁦2026-12-08⁩ → ⁦2026-12-08⁩Float: ⁦32⁩dDrag to change its datesTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-07-18⁩ → ⁦2026-11-30⁩Forecast: ⁦2026-11-29⁩ → ⁦2027-01-09⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-07-18⁩ → ⁦2026-10-09⁩Forecast: ⁦2026-11-29⁩ → ⁦2026-12-24⁩Float: ⁦0⁩dDrag to change its dates+76
Go-live & handoverPlanned: ⁦2026-09-08⁩ → ⁦2026-11-30⁩Forecast: ⁦2026-12-15⁩ → ⁦2027-01-09⁩Float: ⁦0⁩dDrag to change its dates+40
Final handoverPlanned: ⁦2026-11-30⁩ → ⁦2026-11-30⁩Forecast: ⁦2027-01-09⁩ → ⁦2027-01-09⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦6⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦4⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“System testing” needs a pace ⁦3.5⁩× faster than it has kept

It earned ⁦70%⁩ in 206 days; the forecast assumes the rest in 25 days. At the pace so far it finishes on ⁦2027-01-24⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 98 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

60
106
173
112
40
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close