PRJ-2026-003At risk4ExecutionWaterfallIn progressDelivered by:Ministry of Communications and Information Technology

Government Backup Data Centre, Homs — Phase 2

Add to watchlist

A Tier III standby site in Homs, away from the capital, that keeps the government e-services platform and the ministries’ systems running after a major outage at the main Damascus data centre.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.7B

Actual cost

SYP 2.9B

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SYP 4.1B

+SYP 365.9M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
PSA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-04-13⁩
ApprovedMTG-KO-003Kick-off — Government Backup Data Centre, Homs — Phase 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-003
Project
Government Backup Data Centre, Homs — Phase 2
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. George Haddad

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Government Backup Data Centre, Homs — Phase 2
Date and timeAuto-filled
⁦2025-04-13⁩ · 10:00
PlaceAuto-filled
Main meeting room — Authority HQ, Kafr Sousa
SecretaryAuto-filled
Eng. George Haddad

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Khaled Al-KayyaliDeputy President, Digital Transformation
Eng. Mazen KassabDirector General, Government Digital Infrastructure
Eng. George HaddadDirector, Data Centres & Government Network
Dr. Reem Al-QabbaniDirector, National Project Management Office
Eng. Mazen KassabDirector General, Government Digital Infrastructure

2Roles

PersonRoleDuty
Eng. Khaled Al-KayyaliProject sponsorSponsors the project, decides escalations and material changes
Eng. Mazen KassabProject ownerApproves the requirements and accepts the deliverables
Eng. George HaddadProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Reem Al-QabbaniProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Mazen KassabProject ownerDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. George Haddad⁦2025-08-19⁩Done
Designs approvedEng. George Haddad⁦2025-12-01⁩Done
Build completeEng. George Haddad⁦2026-05-06⁩Done
Testing & acceptance completeEng. George Haddad⁦2026-08-18⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. Project Approval Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-07-11⁩
Start confirmed
Eng. Khaled Al-Kayyali · ⁦2025-04-14⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. George HaddadDirector, Data Centres & Government NetworkSubmitted—⁦2025-04-14⁩ 14:35
2Chair’s approval (sponsor)Technical acceptanceEng. Khaled Al-KayyaliProject sponsorApproved—⁦2025-04-15⁩ 12:30
3Minutes against the templateMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-04-16⁩ 12:09

Signatures

Minutes against the template

Mariam Al-Zoubi

Approved⁦2025-04-16⁩

Chair’s approval (sponsor)

Eng. Khaled Al-Kayyali

Approved⁦2025-04-15⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. George Haddad on ⁦2025-04-14⁩

  1. Methodology review

    Minutes against the template

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-04-16⁩ at ⁦12:09⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Khaled Al-Kayyali · Project sponsor

    Approved · ⁦2025-04-15⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-04-13⁩

    The minutes as taken

    Eng. George Haddad

Only one version so far.