PSA/2025/003
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SYP 170M — if approved the value becomes SYP 1.2B
64% of the current value paid
Paid
SYP660Mof a current value of SYP 1B
Value of each certificate
The last 13 — gross and net
Approved: 13
Count: 13 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 13September 2026 | 2026-10-06 | SYP24.5M | SYP2.5M | SYP2.5M | SYP19.6M | Approved | |
| Certificate 12July 2026 | 2026-08-20 | SYP36.8M | SYP3.7M | SYP3.7M | SYP29.4M | Approved | |
| Certificate 11June 2026 | 2026-07-04 | SYP43.5M | SYP4.4M | SYP4.4M | SYP34.8M | Approved | |
| Certificate 10April 2026 | 2026-05-18 | SYP62M | SYP6.2M | SYP6.2M | SYP49.6M | Approved | |
| Certificate 9March 2026 | 2026-03-31 | SYP60.5M | SYP6.1M | SYP6.1M | SYP48.4M | Approved | |
| Certificate 8January 2026 | 2026-02-12 | SYP65M | SYP6.5M | SYP6.5M | SYP52M | Approved | |
| Certificate 7December 2025 | 2025-12-27 | SYP76.5M | SYP7.7M | SYP7.7M | SYP61.2M | Approved | |
| Certificate 6October 2025 | 2025-11-10 | SYP61.3M | SYP6.1M | SYP6.1M | SYP49M | Approved | |
| Certificate 5September 2025 | 2025-09-24 | SYP65M | SYP6.5M | SYP6.5M | SYP52M | Approved | |
| Certificate 4July 2025 | 2025-08-08 | SYP59.8M | SYP6M | SYP6M | SYP47.8M | Approved | |
| Certificate 3June 2025 | 2025-06-21 | SYP42.8M | SYP4.3M | SYP4.3M | SYP34.2M | Approved | |
| Certificate 2April 2025 | 2025-05-05 | SYP38.3M | SYP3.8M | SYP3.8M | SYP30.6M | Approved | |
| Certificate 1February 2025 | 2025-03-19 | SYP24.3M | SYP2.4M | SYP2.4M | SYP19.4M | Approved |