PSA/2024/019
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SYP 562.5M — if approved the value becomes SYP 6.5B
41% of the current value paid
Paid
SYP2.5Bof a current value of SYP 5.9B
Value of each certificate
The last 14 — gross and net
Approved: 16
Count: 17 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 17September 2026 | 2026-10-14 | SYP147.5M | SYP14.8M | SYP14.8M | SYP118M | Submitted | |
| Certificate 16August 2026 | 2026-09-14 | SYP157.5M | SYP15.8M | SYP15.8M | SYP126M | Approved | |
| Certificate 15July 2026 | 2026-08-13 | SYP72M | SYP7.2M | SYP7.2M | SYP57.6M | Approved | |
| Certificate 14June 2026 | 2026-06-29 | SYP95.3M | SYP9.5M | SYP9.5M | SYP76.2M | Approved | |
| Certificate 13April 2026 | 2026-05-14 | SYP139.3M | SYP13.9M | SYP13.9M | SYP111.4M | Approved | |
| Certificate 12March 2026 | 2026-03-30 | SYP161M | SYP16.1M | SYP16.1M | SYP128.8M | Approved | |
| Certificate 11January 2026 | 2026-02-12 | SYP164.3M | SYP16.4M | SYP16.4M | SYP131.4M | Approved | |
| Certificate 10December 2025 | 2025-12-29 | SYP216.8M | SYP21.7M | SYP21.7M | SYP173.4M | Approved | |
| Certificate 9October 2025 | 2025-11-13 | SYP196.5M | SYP19.7M | SYP19.7M | SYP157.2M | Approved | |
| Certificate 8September 2025 | 2025-09-29 | SYP201M | SYP20.1M | SYP20.1M | SYP160.8M | Approved | |
| Certificate 7July 2025 | 2025-08-15 | SYP228M | SYP22.8M | SYP22.8M | SYP182.4M | Approved | |
| Certificate 6June 2025 | 2025-06-30 | SYP177.8M | SYP17.8M | SYP17.8M | SYP142.2M | Approved | |
| Certificate 5April 2025 | 2025-05-16 | SYP184.3M | SYP18.4M | SYP18.4M | SYP147.4M | Approved | |
| Certificate 4March 2025 | 2025-03-31 | SYP167.5M | SYP16.8M | SYP16.8M | SYP134M | Approved | |
| Certificate 3January 2025 | 2025-02-14 | SYP120.5M | SYP12.1M | SYP12.1M | SYP96.4M | Approved | |
| Certificate 2December 2024 | 2024-12-30 | SYP107.8M | SYP10.8M | SYP10.8M | SYP86.2M | Approved | |
| Certificate 1October 2024 | 2024-11-15 | SYP70.8M | SYP7.1M | SYP7.1M | SYP56.6M | Approved |