Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 10
- Date
- 2025-12-29
- Reference
- PAY-2024-019-10
Interim payment certificate no. (10)
For the work of December 2025
- Contract number
- PSA/2024/019
- Tender file no.
- 2402340251
- Contract
- Sheikh Najjar industrial city — civil & ground-improvement works
- Contractor
- Al-Sahel Contracting & Development Co.
- Contractor tax number
- TX-437644
- Project
- Sheikh Najjar Industrial City Rehabilitation
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- SYP5,700,000,000
- Current contract value
- SYP5,940,000,000including variations of SYP 240M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,670,750,000 |
| 2 | Less: previous certificates | (1,454,000,000) |
| 3 | Value of work in this certificate | 216,750,000 |
| 4 | Less: retention (10%) | (21,675,000) |
| 5 | Less: advance payment recovery (10%) | (21,675,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (43,350,000) |
| 8 | Net amount payable to the contractor | SYP173,400,000 |
Amount in words: One hundred seventy-three million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 167.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 415,800,000 | 237,750,000 | 32,100,000 | 269,850,000 | 65% |
| Earthworks & foundations | 1,069,200,000 | 369,750,000 | 51,275,000 | 421,025,000 | 39% |
| Concrete & structural works | 1,841,400,000 | 495,500,000 | 74,225,000 | 569,725,000 | 31% |
| Mechanical, electrical & plumbing | 1,425,600,000 | 240,925,000 | 39,750,000 | 280,675,000 | 20% |
| Finishes & external works | 891,000,000 | 96,000,000 | 16,775,000 | 112,775,000 | 13% |
| Testing & commissioning | 297,000,000 | 14,075,000 | 2,625,000 | 16,700,000 | 6% |
| Total | 5,940,000,000 | 1,454,000,000 | 216,750,000 | 1,670,750,000 | 28% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ali Deeb
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Youssef Shehabi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar