Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦15⁩ — July 2026

Sheikh Najjar industrial city — civil & ground-improvement works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
15
Date
⁦2026-08-13⁩
Reference
PAY-2024-019-15

Interim payment certificate no. (⁦15⁩)

For the work of July 2026

Contract number
PSA/2024/019
Tender file no.
2402340251
Contract
Sheikh Najjar industrial city — civil & ground-improvement works
Contractor
Al-Sahel Contracting & Development Co.
Contractor tax number
TX-437644
Project
Sheikh Najjar Industrial City Rehabilitation
Contract period
⁦2024-10-01⁩ — ⁦2027-03-31⁩
Original contract value
SYP5,700,000,000
Current contract value
SYP5,940,000,000including variations of SYP 240M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date2,302,500,000
2Less: previous certificates(2,230,500,000)
3Value of work in this certificate72,000,000
4Less: retention (⁦10%⁩)(7,200,000)
5Less: advance payment recovery (⁦10%⁩)(7,200,000)
6Less: delay and breach penalties0
7Total deductions(14,400,000)
8Net amount payable to the contractorSYP57,600,000

Amount in words: Fifty-seven million six hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 230.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation415,800,000361,700,00010,150,000371,850,000⁦89%⁩
Earthworks & foundations1,069,200,000563,775,00016,450,000580,225,000⁦54%⁩
Concrete & structural works1,841,400,000760,425,00024,725,000785,150,000⁦43%⁩
Mechanical, electrical & plumbing1,425,600,000373,050,00013,775,000386,825,000⁦27%⁩
Finishes & external works891,000,000149,475,0005,950,000155,425,000⁦17%⁩
Testing & commissioning297,000,00022,075,000950,00023,025,000⁦8%⁩
Total5,940,000,0002,230,500,00072,000,0002,302,500,000⁦39%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ali Deeb

Deeb⁦2026-08-13⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-08-15⁩

Project manager

Eng. Youssef Shehabi

Shehabi⁦2026-08-18⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-08-21⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-08-24⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-08-13⁩

    Eng. Ali Deeb

  2. Engineer verifies quantities⁦2026-08-15⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-08-18⁩

    Eng. Youssef Shehabi · Senior Project Manager — Governorate Projects

    Took 3 days

  4. Payment order prepared⁦2026-08-21⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-08-24⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-14⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Youssef Shehabi → Dr. Samer Al-Daqqar

Certificate history

24 August 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-08-24 13:00

21 August 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-08-21 13:00

18 August 2026

  1. Approval: Eng. Youssef Shehabi signed “Project manager certifies”

    2026-08-18 13:00

15 August 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-08-15 13:00

13 August 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-08-13 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close