Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 3
- Date
- 2025-02-14
- Reference
- PAY-2024-019-03
Interim payment certificate no. (3)
For the work of January 2025
- Contract number
- PSA/2024/019
- Tender file no.
- 2402340251
- Contract
- Sheikh Najjar industrial city — civil & ground-improvement works
- Contractor
- Al-Sahel Contracting & Development Co.
- Contractor tax number
- TX-437644
- Project
- Sheikh Najjar Industrial City Rehabilitation
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- SYP5,700,000,000
- Current contract value
- SYP5,940,000,000including variations of SYP 240M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SYP)
| 1 | Total value of work completed to date | 299,000,000 |
| 2 | Less: previous certificates | (178,500,000) |
| 3 | Value of work in this certificate | 120,500,000 |
| 4 | Less: retention (10%) | (12,050,000) |
| 5 | Less: advance payment recovery (10%) | (12,050,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (24,100,000) |
| 8 | Net amount payable to the contractor | SYP96,400,000 |
Amount in words: Ninety-six million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 29.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 415,800,000 | 29,075,000 | 19,225,000 | 48,300,000 | 12% |
| Earthworks & foundations | 1,069,200,000 | 45,250,000 | 30,100,000 | 75,350,000 | 7% |
| Concrete & structural works | 1,841,400,000 | 60,825,000 | 41,125,000 | 101,950,000 | 6% |
| Mechanical, electrical & plumbing | 1,425,600,000 | 29,700,000 | 20,525,000 | 50,225,000 | 4% |
| Finishes & external works | 891,000,000 | 11,875,000 | 8,300,000 | 20,175,000 | 2% |
| Testing & commissioning | 297,000,000 | 1,775,000 | 1,225,000 | 3,000,000 | 1% |
| Total | 5,940,000,000 | 178,500,000 | 120,500,000 | 299,000,000 | 5% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ali Deeb
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Youssef Shehabi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar