Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 5
- Date
- 2025-05-16
- Reference
- PAY-2024-019-05
Interim payment certificate no. (5)
For the work of April 2025
- Contract number
- PSA/2024/019
- Tender file no.
- 2402340251
- Contract
- Sheikh Najjar industrial city — civil & ground-improvement works
- Contractor
- Al-Sahel Contracting & Development Co.
- Contractor tax number
- TX-437644
- Project
- Sheikh Najjar Industrial City Rehabilitation
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- SYP5,700,000,000
- Current contract value
- SYP5,940,000,000including variations of SYP 240M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SYP)
| 1 | Total value of work completed to date | 650,750,000 |
| 2 | Less: previous certificates | (466,500,000) |
| 3 | Value of work in this certificate | 184,250,000 |
| 4 | Less: retention (10%) | (18,425,000) |
| 5 | Less: advance payment recovery (10%) | (18,425,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (36,850,000) |
| 8 | Net amount payable to the contractor | SYP147,400,000 |
Amount in words: One hundred forty-seven million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 65.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 415,800,000 | 76,175,000 | 28,925,000 | 105,100,000 | 25% |
| Earthworks & foundations | 1,069,200,000 | 118,525,000 | 45,475,000 | 164,000,000 | 15% |
| Concrete & structural works | 1,841,400,000 | 158,975,000 | 62,925,000 | 221,900,000 | 12% |
| Mechanical, electrical & plumbing | 1,425,600,000 | 77,400,000 | 31,925,000 | 109,325,000 | 8% |
| Finishes & external works | 891,000,000 | 30,875,000 | 13,050,000 | 43,925,000 | 5% |
| Testing & commissioning | 297,000,000 | 4,550,000 | 1,950,000 | 6,500,000 | 2% |
| Total | 5,940,000,000 | 466,500,000 | 184,250,000 | 650,750,000 | 11% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ali Deeb
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Youssef Shehabi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar