PSA/2024/005
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
73% of the current value paid
Paid
SYP267.5Mof a current value of SYP 365M
Value of each certificate
The last 14 — gross and net
Approved: 21
Count: 21 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 21September 2026 | 2026-10-06 | SYP6M | SYP300K | SYP0 | SYP5.7M | Approved | |
| Certificate 20July 2026 | 2026-08-20 | SYP7.3M | SYP362.5K | SYP0 | SYP6.9M | Approved | |
| Certificate 19June 2026 | 2026-07-05 | SYP8.8M | SYP437.5K | SYP0 | SYP8.3M | Approved | |
| Certificate 18April 2026 | 2026-05-19 | SYP12M | SYP600K | SYP0 | SYP11.4M | Approved | |
| Certificate 17March 2026 | 2026-04-02 | SYP11.5M | SYP575K | SYP0 | SYP10.9M | Approved | |
| Certificate 16January 2026 | 2026-02-15 | SYP14M | SYP700K | SYP0 | SYP13.3M | Approved | |
| Certificate 15December 2025 | 2025-12-30 | SYP16.3M | SYP812.5K | SYP0 | SYP15.4M | Approved | |
| Certificate 14October 2025 | 2025-11-13 | SYP14.5M | SYP725K | SYP0 | SYP13.8M | Approved | |
| Certificate 13September 2025 | 2025-09-28 | SYP18M | SYP900K | SYP0 | SYP17.1M | Approved | |
| Certificate 12July 2025 | 2025-08-12 | SYP17.5M | SYP875K | SYP0 | SYP16.6M | Approved | |
| Certificate 11June 2025 | 2025-06-27 | SYP15.8M | SYP787.5K | SYP0 | SYP15M | Approved | |
| Certificate 10April 2025 | 2025-05-11 | SYP19M | SYP950K | SYP0 | SYP18.1M | Approved | |
| Certificate 9March 2025 | 2025-03-25 | SYP16M | SYP800K | SYP0 | SYP15.2M | Approved | |
| Certificate 8January 2025 | 2025-02-07 | SYP15.5M | SYP775K | SYP0 | SYP14.7M | Approved | |
| Certificate 7December 2024 | 2024-12-22 | SYP16.8M | SYP837.5K | SYP0 | SYP15.9M | Approved | |
| Certificate 6October 2024 | 2024-11-05 | SYP12.8M | SYP637.5K | SYP0 | SYP12.1M | Approved | |
| Certificate 5August 2024 | 2024-09-20 | SYP12.8M | SYP637.5K | SYP0 | SYP12.1M | Approved | |
| Certificate 4July 2024 | 2024-08-04 | SYP11.5M | SYP575K | SYP0 | SYP10.9M | Approved | |
| Certificate 3May 2024 | 2024-06-18 | SYP8.5M | SYP425K | SYP0 | SYP8.1M | Approved | |
| Certificate 2April 2024 | 2024-05-03 | SYP7.8M | SYP387.5K | SYP0 | SYP7.4M | Approved | |
| Certificate 1February 2024 | 2024-03-17 | SYP5.5M | SYP275K | SYP0 | SYP5.2M | Approved |