Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦16⁩ — January 2026

Engineering supervision — Aleppo substations rehabilitation

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
16
Date
⁦2026-02-15⁩
Reference
PAY-2024-005-16

Interim payment certificate no. (⁦16⁩)

For the work of January 2026

Contract number
PSA/2024/005
Tender file no.
2401360069
Contract
Engineering supervision — Aleppo substations rehabilitation
Contractor
Al-Assi Project Management Group
Contractor tax number
TX-425096
Project
Aleppo 230 kV Substations Rehabilitation
Contract period
⁦2024-02-01⁩ — ⁦2027-03-31⁩
Original contract value
SYP365,000,000
Current contract value
SYP365,000,000
Linked milestone
Supervision to provisional acceptance · MS-G5 Final handover

Certificate summary (SYP)

1Total value of work completed to date222,000,000
2Less: previous certificates(208,000,000)
3Value of work in this certificate14,000,000
4Less: retention (⁦5%⁩)(700,000)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(700,000)
8Net amount payable to the contractorSYP13,300,000

Amount in words: Thirteen million three hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 11.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff226,300,000129,825,0008,725,000138,550,000⁦61%⁩
Visiting specialists65,700,00037,425,0002,525,00039,950,000⁦61%⁩
Laboratory & testing43,800,00022,375,0001,600,00023,975,000⁦55%⁩
Reporting & technical office29,200,00018,375,0001,150,00019,525,000⁦67%⁩
Total365,000,000208,000,00014,000,000222,000,000⁦61%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ramez Al-Omar

Al-Omar⁦2026-02-15⁩

Supervising engineer

Huda Al-Dandal

Al-Dandal⁦2026-02-17⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-02-20⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-02-23⁩

Final approver

Rasha Al-Mudarres

Al-Mudarres⁦2026-02-26⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-15⁩

    Eng. Ramez Al-Omar

  2. Engineer verifies quantities⁦2026-02-17⁩

    Huda Al-Dandal · Senior Financial Analyst — Investment Plan

    Took 2 days

  3. Project manager certifies⁦2026-02-20⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-02-23⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-02-26⁩

    Rasha Al-Mudarres · Director General, Finance & Contracts

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSupervision to provisional acceptanceLate · ⁦2026-10-09⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Rasha Al-Mudarres
  • Whoever verified quantities does not prepare the payment orderHuda Al-Dandal → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Rasha Al-Mudarres

Certificate history

26 February 2026

  1. Payment: Rasha Al-Mudarres signed “Final approval”

    2026-02-26 13:00

23 February 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-02-23 13:00

20 February 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-02-20 13:00

17 February 2026

  1. Approval: Huda Al-Dandal signed “Engineer verifies quantities”

    2026-02-17 13:00

15 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-15 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close