Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦17⁩ — March 2026

Engineering supervision — Aleppo substations rehabilitation

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
17
Date
⁦2026-04-02⁩
Reference
PAY-2024-005-17

Interim payment certificate no. (⁦17⁩)

For the work of March 2026

Contract number
PSA/2024/005
Tender file no.
2401360069
Contract
Engineering supervision — Aleppo substations rehabilitation
Contractor
Al-Assi Project Management Group
Contractor tax number
TX-425096
Project
Aleppo 230 kV Substations Rehabilitation
Contract period
⁦2024-02-01⁩ — ⁦2027-03-31⁩
Original contract value
SYP365,000,000
Current contract value
SYP365,000,000
Linked milestone
Supervision to provisional acceptance · MS-G5 Final handover

Certificate summary (SYP)

1Total value of work completed to date233,500,000
2Less: previous certificates(222,000,000)
3Value of work in this certificate11,500,000
4Less: retention (⁦5%⁩)(575,000)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(575,000)
8Net amount payable to the contractorSYP10,925,000

Amount in words: Ten million nine hundred twenty-five thousand Syrian pounds only

Retention held up to this certificate: SYP 11.7M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff226,300,000138,525,0007,175,000145,700,000⁦64%⁩
Visiting specialists65,700,00039,950,0002,075,00042,025,000⁦64%⁩
Laboratory & testing43,800,00023,900,0001,325,00025,225,000⁦58%⁩
Reporting & technical office29,200,00019,625,000925,00020,550,000⁦70%⁩
Total365,000,000222,000,00011,500,000233,500,000⁦64%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ramez Al-Omar

Al-Omar⁦2026-04-02⁩

Supervising engineer

Huda Al-Dandal

Al-Dandal⁦2026-04-04⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-04-07⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-04-10⁩

Final approver

Rasha Al-Mudarres

Al-Mudarres⁦2026-04-13⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-04-02⁩

    Eng. Ramez Al-Omar

  2. Engineer verifies quantities⁦2026-04-04⁩

    Huda Al-Dandal · Senior Financial Analyst — Investment Plan

    Took 2 days

  3. Project manager certifies⁦2026-04-07⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-04-10⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-04-13⁩

    Rasha Al-Mudarres · Director General, Finance & Contracts

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSupervision to provisional acceptanceLate · ⁦2026-10-09⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Rasha Al-Mudarres
  • Whoever verified quantities does not prepare the payment orderHuda Al-Dandal → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Rasha Al-Mudarres

Certificate history

13 April 2026

  1. Payment: Rasha Al-Mudarres signed “Final approval”

    2026-04-13 13:00

10 April 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-04-10 13:00

7 April 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-04-07 13:00

4 April 2026

  1. Approval: Huda Al-Dandal signed “Engineer verifies quantities”

    2026-04-04 13:00

2 April 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-04-02 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close