PRJ-2026-030On track5ClosureWaterfallIn progressDelivered by:Planning and Statistics Authority

National Project Risk & Continuity Framework

Add to watchlist

One policy and set of registers for national project risk and business continuity, adopted by the ministries, with training for risk coordinators.

Project managerNizar Abu FakhrProject sponsorDr. Ziad Al-Atassi

Budget (BAC)

SYP 90M

Actual cost

SYP 86.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 86.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+56⁩ days vs approved

Baseline (original = approved) · By earned schedule⁦2026-08-31⁩
Current forecast⁦2026-10-26⁩
Critical activities
0
of ⁦0⁩ open activities
Late activities
0
past their baseline finish
Schedule performance
1.00
earned ÷ planned value
Breached constraints
0
binding dates that will be missed
Expand allCollapse all
Activity
National Project Risk & Continuity FrameworkPlanned: ⁦2025-03-09⁩ → ⁦2026-08-31⁩Actual: ⁦2025-03-09⁩ → ⁦2026-10-26⁩
Management & governancePlanned: ⁦2025-03-09⁩ → ⁦2025-07-19⁩Actual: ⁦2025-03-09⁩ → ⁦2025-08-03⁩
Project plan & baselinePlanned: ⁦2025-03-09⁩ → ⁦2025-05-30⁩Actual: ⁦2025-03-09⁩ → ⁦2025-06-07⁩
Monitoring & reportingPlanned: ⁦2025-04-29⁩ → ⁦2025-07-19⁩Actual: ⁦2025-05-04⁩ → ⁦2025-08-03⁩
Project plan approvedPlanned: ⁦2025-07-19⁩ → ⁦2025-07-19⁩Actual: ⁦2025-08-03⁩ → ⁦2025-08-03⁩Project plan approved
DiagnosisPlanned: ⁦2025-06-19⁩ → ⁦2025-10-29⁩Actual: ⁦2025-06-30⁩ → ⁦2025-11-24⁩
Current-state assessmentPlanned: ⁦2025-06-19⁩ → ⁦2025-09-08⁩Actual: ⁦2025-06-30⁩ → ⁦2025-09-28⁩
BenchmarkingPlanned: ⁦2025-08-09⁩ → ⁦2025-10-29⁩Actual: ⁦2025-08-25⁩ → ⁦2025-11-24⁩
Designs approvedPlanned: ⁦2025-10-29⁩ → ⁦2025-10-29⁩Actual: ⁦2025-11-24⁩ → ⁦2025-11-24⁩Designs approved
DesignPlanned: ⁦2025-09-29⁩ → ⁦2026-02-08⁩Actual: ⁦2025-10-21⁩ → ⁦2026-03-16⁩
Target modelPlanned: ⁦2025-09-29⁩ → ⁦2025-12-19⁩Actual: ⁦2025-10-21⁩ → ⁦2026-01-19⁩
RoadmapPlanned: ⁦2025-11-19⁩ → ⁦2026-02-08⁩Actual: ⁦2025-12-16⁩ → ⁦2026-03-16⁩
Build completePlanned: ⁦2026-02-08⁩ → ⁦2026-02-08⁩Actual: ⁦2026-03-16⁩ → ⁦2026-03-16⁩Build complete
ImplementationPlanned: ⁦2026-01-09⁩ → ⁦2026-05-21⁩Actual: ⁦2026-02-10⁩ → ⁦2026-07-07⁩
Wave 1Planned: ⁦2026-01-09⁩ → ⁦2026-03-31⁩Actual: ⁦2026-02-10⁩ → ⁦2026-05-12⁩
Wave 2Planned: ⁦2026-03-01⁩ → ⁦2026-05-21⁩Actual: ⁦2026-04-08⁩ → ⁦2026-07-07⁩
Testing & acceptance completePlanned: ⁦2026-05-21⁩ → ⁦2026-05-21⁩Actual: ⁦2026-07-07⁩ → ⁦2026-07-07⁩Testing & acceptance complete
Handover & knowledge transferPlanned: ⁦2026-04-21⁩ → ⁦2026-08-31⁩Actual: ⁦2026-06-03⁩ → ⁦2026-10-26⁩
Knowledge transferPlanned: ⁦2026-04-21⁩ → ⁦2026-07-11⁩Actual: ⁦2026-06-03⁩ → ⁦2026-09-02⁩
Final reportPlanned: ⁦2026-06-10⁩ → ⁦2026-08-31⁩Actual: ⁦2026-07-30⁩ → ⁦2026-10-26⁩
Final handoverPlanned: ⁦2026-08-31⁩ → ⁦2026-08-31⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Final handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦21⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦0⁩ open activities, data date ⁦2026-10-28⁩

Slippage pattern⁦84%⁩ confidence

Milestones slip 36 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

15
26
36
47
56
G1G2G3G4G5

The critical chain

In date order, to final acceptance

No open critical activities