National Project Risk & Continuity Framework
Add to watchlistOne policy and set of registers for national project risk and business continuity, adopted by the ministries, with training for risk coordinators.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-07-19 | 2025-08-03 | +15 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-29 | 2025-11-24 | +26 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-02-08 | 2026-03-16 | +36 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-05-21 | 2026-07-07 | +47 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-08-31 | 2026-10-26 | +56 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
100%Awaiting acceptance
0%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline030-D1 | 5% | CRT-030-01 | Approved | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Dr. Mais Al-Sibai | 2025-05-30 | V1 | 3 of 3 |
| Monitoring & reporting030-D2 | 5% | CRT-030-02 | Approved | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2025-07-19 | V1 | 3 of 3 |
| Current-state assessment030-D3 | 10% | CRT-030-03 | Approved | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2025-09-08 | V1 | 3 of 3 |
| Benchmarking030-D4 | 10% | CRT-030-04 | Approved | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2025-10-29 | V1 | 3 of 3 |
| Target model030-D5 | 15% | CRT-030-05 | Approved | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2025-12-19 | V1 | 3 of 3 |
| Roadmap030-D6 | 15% | CRT-030-06 | Approved | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Dr. Mais Al-Sibai | 2026-02-08 | V1 | 3 of 3 |
| Wave 1030-D7 | 15% | CRT-030-07 | Approved | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Dr. Mais Al-Sibai | 2026-03-31 | V1 | 3 of 3 |
| Wave 2030-D8 | 15% | CRT-030-08 | Approved | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-05-21 | V1 | 3 of 3 |
| Knowledge transfer030-D9 | 5% | CRT-030-09 | Approved | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-07-11 | V1 | 3 of 3 |
| Final report030-D10 | 5% | CRT-030-10 | Approved | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2026-08-31 | V1 | 3 of 3 |
| Total · 10 | 100% |