PRJ-2026-030On track5ClosureWaterfallIn progressDelivered by:Planning and Statistics Authority

National Project Risk & Continuity Framework

Add to watchlist

One policy and set of registers for national project risk and business continuity, adopted by the ministries, with training for risk coordinators.

Project managerNizar Abu FakhrProject sponsorDr. Ziad Al-Atassi

Budget (BAC)

SYP 90M

Actual cost

SYP 86.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 86.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
PSA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-03-16⁩
ApprovedMTG-KO-030Kick-off — National Project Risk & Continuity Framework

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-030
Project
National Project Risk & Continuity Framework
Portfolio
Planning, Statistics & Capability Portfolio
Sector
Strategy & National PMO Sector
Sponsor
Dr. Ziad Al-Atassi
Project manager
Nizar Abu Fakhr

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — National Project Risk & Continuity Framework
Date and timeAuto-filled
⁦2025-03-16⁩ · 10:00
PlaceAuto-filled
Main meeting room — Authority HQ, Kafr Sousa
SecretaryAuto-filled
Nizar Abu Fakhr

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Dr. Ziad Al-AtassiDeputy President, Strategy & Performance
Dr. Mais Al-SibaiDirector General, Strategy & National Projects
Nizar Abu FakhrHead, Monitoring, Evaluation & Performance
Dr. Reem Al-QabbaniDirector, National Project Management Office
Dr. Reem Al-QabbaniDirector, National Project Management Office

2Roles

PersonRoleDuty
Dr. Ziad Al-AtassiProject sponsorSponsors the project, decides escalations and material changes
Dr. Mais Al-SibaiProject ownerApproves the requirements and accepts the deliverables
Nizar Abu FakhrProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Reem Al-QabbaniProject Management OfficeFollows the methodology and checks the periodic updates
Dr. Reem Al-QabbaniClosure assurance & lessons learnedDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedNizar Abu Fakhr⁦2025-07-19⁩Done
Designs approvedNizar Abu Fakhr⁦2025-10-29⁩Done
Build completeNizar Abu Fakhr⁦2026-02-08⁩Done
Testing & acceptance completeNizar Abu Fakhr⁦2026-05-21⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. Project Approval Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-06-03⁩
Start confirmed
Dr. Ziad Al-Atassi · ⁦2025-03-17⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Nizar Abu FakhrHead, Monitoring, Evaluation & PerformanceSubmitted—⁦2025-03-17⁩ 14:05
2Chair’s approval (sponsor)Technical acceptanceDr. Ziad Al-AtassiProject sponsorApproved—⁦2025-03-18⁩ 12:30
3Minutes against the templateMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-03-19⁩ 12:39

Signatures

Minutes against the template

Mariam Al-Zoubi

Approved⁦2025-03-19⁩

Chair’s approval (sponsor)

Dr. Ziad Al-Atassi

Approved⁦2025-03-18⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Nizar Abu Fakhr on ⁦2025-03-17⁩

  1. Methodology review

    Minutes against the template

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-03-19⁩ at ⁦12:39⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Dr. Ziad Al-Atassi · Project sponsor

    Approved · ⁦2025-03-18⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-03-16⁩