Baniyas Pilot Seawater Desalination Plant
Add to watchlistA pilot seawater desalination plant in Baniyas to test the technology and cost before scaling along the coast — paused while its allocation in the investment plan is confirmed.
Budget (BAC)
Actual cost
8% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
123 days behind baseline
PlanningStage 3 of 5
Next gate:Execution24 April 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-05-18 | 2026-10-26 | +161 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-08-08 | 2027-01-16 | +161 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Late | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2026-12-08 | 2027-05-04 | +147 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-04-09 | 2027-08-20 | +133 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-06-30 | 2027-10-31 | +123 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
8%Awaiting acceptance
6%Not handed in
86%Deliverable flow
Display options
| Project plan & baseline026-D1 | 4% | CRT-026-01 | Approved | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Eng. Wassim Al-Azm | 2026-04-07 | V1 | 3 of 3 |
| Monitoring & reporting026-D2 | 4% | CRT-026-02 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-05-18 | V1 | 3 of 3 |
| Detailed design026-D3 | 6% | — | Submitted | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-06-28 | V1 | 1 of 3 |
| Permits & approvals026-D4 | 6% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2026-08-08 | V0 | 0 of 3 |
| Site works & excavation026-D5 | 12% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2026-09-17 | V0 | 0 of 3 |
| Structure026-D6 | 12% | — | Draft | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Eng. Wassim Al-Azm | 2026-10-28 | V0 | 0 of 3 |
| Finishes026-D7 | 12% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-12-08 | V0 | 0 of 3 |
| Supply026-D8 | 10% | — | Draft | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Eng. Wassim Al-Azm | 2027-01-18 | V0 | 0 of 3 |
| Installation026-D9 | 10% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-02-28 | V0 | 0 of 3 |
| Testing & commissioning026-D10 | 10% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2027-04-09 | V0 | 0 of 3 |
| Provisional acceptance026-D11 | 7% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-05-20 | V0 | 0 of 3 |
| Final acceptance026-D12 | 7% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2027-06-30 | V0 | 0 of 3 |
| Total · 12 | 100% |