PRJ-2026-026On hold3PlanningWaterfallStoppedDelivered by:Ministry of Energy

Baniyas Pilot Seawater Desalination Plant

Add to watchlist

A pilot seawater desalination plant in Baniyas to test the technology and cost before scaling along the coast — paused while its allocation in the investment plan is confirmed.

Budget (BAC)

SYP 825M

Actual cost

SYP 66M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SYP 825M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
PSA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2025-08-30⁩
ApprovedPRJ-2026-026Baniyas Pilot Seawater Desalination Plant

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-026
Project
Baniyas Pilot Seawater Desalination Plant
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Rami Youssef

1The resultAuto-filled

Priority score

58 of 100

Class

P3

45–59

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the development framework⁦20%⁩4.517.5
Development value⁦12%⁩3.78.1
Economic & social return⁦8%⁩3.34.6
Urgency⁦10%⁩3.46.0
Legal requirement⁦10%⁩1.61.5
Risk⁦7%⁩3.03.5
Complexity⁦6%⁩3.22.7
Resource requirement⁦5%⁩1.14.9
Impact on citizens & beneficiaries⁦14%⁩2.96.7
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩2.11.4
Total⁦100%⁩—58

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2025-08-30⁩ 11:38
2Evaluation checked against the modelMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-08-31⁩ 09:42
3Portfolio manager reviewTechnical acceptanceEng. Rami YoussefPortfolio managerApproved—⁦2025-09-02⁩ 10:49
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2025-09-08⁩ 11:56

Signatures

Evaluation checked against the model

Mariam Al-Zoubi

Approved⁦2025-08-31⁩

Portfolio manager review

Eng. Rami Youssef

Approved⁦2025-09-02⁩

Class approved — Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2025-09-08⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2025-08-30⁩

  1. Methodology review

    Evaluation checked against the model

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-08-31⁩ at ⁦09:42⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Rami Youssef · Portfolio manager

    Approved · ⁦2025-09-02⁩ at ⁦10:49⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2025-09-08⁩ at ⁦11:56⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2025-08-30⁩

    Evaluated on the approved priority model

    Mariam Al-Zoubi

Only one version so far.