PRJ-2026-017At risk5ClosureWaterfallIn progressDelivered by:Ministry of Finance

Ministry of Finance e-Archiving

Add to watchlist

Electronic archiving of the Ministry of Finance’s documents and financial correspondence, with a workflow for administrative correspondence and one search across the archive.

Budget (BAC)

SYP 355M

Actual cost

SYP 337.3M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 355M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
PSA-PMO-F12
Template edition
2.0
Version
V0
Form date
⁦2026-10-28⁩
DraftPRJ-2026-017Ministry of Finance e-Archiving

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Ministry of Finance e-Archiving
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Salma Al-Zaim
Project manager
Nour Al-Jabiri

1PerformanceAuto-filled

Approved budget

SYP 355M

Actual cost

SYP 337.3M

Cost variance

+SYP 17.8M

Schedule variance

+46 days

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesOpenRasha Al-MudarresFinal acceptance of every deliverable
Financial settlementOpenOmar Al-NahhasSpend reconciled, commitments closed
Contracts closedOpenOmar Al-NahhasContracts closed, bonds released
Documents archivedOpenNour Al-JabiriDocuments archived with classification
Lessons learnedOpenNour Al-JabiriLessons-learned session
Benefits handed to their ownerOpenRasha Al-MudarresBenefits handed to their owner with a measurement plan
Final reportOpenNour Al-JabiriFinal report and its approval
BenefitNew ownerHandover
Faster routing of correspondenceRasha Al-MudarresPlanned

3Open commitments

CommitmentOwnerDue
Final acceptance of deliverables — Final acceptance of every deliverableRasha Al-Mudarres⁦2026-11-05⁩
Financial settlement — Spend reconciled, commitments closedOmar Al-Nahhas⁦2026-12-05⁩
Contracts closed — Contracts closed, bonds releasedOmar Al-Nahhas⁦2026-12-15⁩
Documents archived — Documents archived with classificationNour Al-Jabiri⁦2026-12-10⁩
Lessons learned — Lessons-learned sessionNour Al-Jabiri⁦2026-11-30⁩
Benefits handed to their owner — Benefits handed to their owner with a measurement planRasha Al-Mudarres⁦2026-11-25⁩
Final report — Final report and its approvalNour Al-Jabiri⁦2026-12-20⁩

4Lessons learnedAuto-filled

  1. —

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

No decisions yet — the form has not been submitted.

Signatures

Closure file completeness

Mariam Al-Zoubi

Later

Handover accepted — project owner

Rasha Al-Mudarres

Later

Final financial settlement

Rasha Al-Mudarres

Later

Contracts closed, guarantees released

Abdullah Al-Ujaili

Later

Project Approval Committee

Dr. Reem Al-Qabbani

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F12 · version V0

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Not submitted for approval yet.

  1. Methodology review

    Closure file completeness

    Mariam Al-Zoubi · PMO — analyst

    Delegated to Dr. Reem Al-Qabbani

  2. Technical acceptance

    Handover accepted — project owner

    Rasha Al-Mudarres · Project owner

    Delegated to Omar Al-Nahhas

  3. Financial approval

    Final financial settlement

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Delegated to Omar Al-Nahhas

  4. Financial approval

    Contracts closed, guarantees released

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee
Waiting on Nour Al-Jabiri

Previous versions

Every version is kept with its status and what changed.

  1. V0DraftCurrent⁦2026-10-28⁩

    The closure file in preparation

    Nour Al-Jabiri

Only one version so far.