PRJ-2026-014 · From item 4
Unified Government e-Services PlatformPlanned to date 67%
- SPI
- 0.87
- Forecast finish
- 2027-05-12
- Budget
- SYP 2.2B
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Sixth meeting of 2026: the 2027 investment plan and annual work plan, and the Q3 strategic performance report.
Scheduled for
16:002026-11-24 · 16:00
135 of 150 min
Approve the previous minutes
ApprovalDr. Nisreen Al-Shoufi
5 min
The 2027 investment plan and annual work plan
DecisionSalma Al-Zaim
60 min
Strategic performance report — Q3 2026
For informationDr. Ziad Al-Atassi
30 min
Re-evaluating the citizen-satisfaction-with-digital-services target
DecisionDr. Ziad Al-Atassi
20 min
Reconstruction & infrastructure — project status
For informationDr. Reem Al-Qabbani
20 min
What will be presented and what needs a decision — read before the meeting
Approve the previous minutes
ApprovalPresented by Dr. Nisreen Al-Shoufi5 min
The 2027 investment plan and annual work plan
DecisionPresented by Salma Al-Zaim60 minAnnual work plan
Needs a committee decision
Strategic performance report — Q3 2026
For informationPresented by Dr. Ziad Al-Atassi30 minDEC-2026-049
Re-evaluating the citizen-satisfaction-with-digital-services target
DecisionPresented by Dr. Ziad Al-Atassi20 minDEC-2026-048
Needs a committee decision
Reconstruction & infrastructure — project status
For informationPresented by Dr. Reem Al-Qabbani20 minPF-INF
From this committee’s earlier meetings and decisions — reviewed at the start
No open tasks carried over
The council’s quorum and votes are recorded in its signed minutes, not in Munjaz
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-014 · From item 4
Unified Government e-Services PlatformPlanned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
PRJ-2026-002 · From item 5
Darayya Replacement HousingPlanned to date 51%
74 days lateMaterial risks: 3Open impediments: 3Corrective plan required
PRJ-2026-020 · From item 5
Douma Wastewater Treatment PlantPlanned to date 55%
64 days lateMaterial risks: 1Open impediments: 1Corrective plan CP-2026-04
Agenda item needing a decision
The 2027 investment plan and annual work planFrom item 2
Agenda item needing a decision · DEC-2026-048
Re-evaluating the citizen-satisfaction-with-digital-services targetFrom item 4
Change request awaiting decision · CR-2026-004
Add civil-record transfer & record merge to the first releaseUnified Government e-Services Platform
Change request awaiting decision · CR-2026-010
Redesign the treatment-basin foundations on axes 12 to 16Douma Wastewater Treatment Plant
Corrective plan awaiting approval · CP-2026-01
Unified Government e-Services PlatformISS-0103 · Unified Government e-Services Platform
PeopleSYP 24.5M· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · Unified Government e-Services Platform
Coordination· Asked from: Dr. Samer Al-Daqqar
A letter from the President of the Authority to the Ministry of Interior for a dedicated test environment for three months
ISS-0116 · Darayya Replacement Housing
Coordination· Asked from: Eng. Wassim Al-Azm
Urgent coordination with the electricity transmission & distribution establishment to divert the line within 30 days
CP-2026-01 · Unified Government e-Services Platform
PeopleSYP 24.5M· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
ACT-0313 · Eng. Wassim Al-Azm