PSA/2025/010
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
85% of the current value paid
Paid
SYP315Mof a current value of SYP 370M
Value of each certificate
The last 11 — gross and net
Approved: 11
Count: 11 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 11September 2026 | 2026-10-06 | SYP14M | SYP700K | SYP1.4M | SYP11.9M | Approved | |
| Certificate 10August 2026 | 2026-08-22 | SYP24M | SYP1.2M | SYP2.4M | SYP20.4M | Approved | |
| Certificate 9June 2026 | 2026-07-09 | SYP27.8M | SYP1.4M | SYP2.8M | SYP23.6M | Approved | |
| Certificate 8May 2026 | 2026-05-25 | SYP33M | SYP1.7M | SYP3.3M | SYP28.1M | Approved | |
| Certificate 7March 2026 | 2026-04-10 | SYP41.8M | SYP2.1M | SYP4.2M | SYP35.5M | Approved | |
| Certificate 6February 2026 | 2026-02-25 | SYP35.3M | SYP1.8M | SYP3.5M | SYP30M | Approved | |
| Certificate 5December 2025 | 2026-01-11 | SYP38.8M | SYP1.9M | SYP3.9M | SYP32.9M | Approved | |
| Certificate 4November 2025 | 2025-11-27 | SYP36.5M | SYP1.8M | SYP3.7M | SYP31M | Approved | |
| Certificate 3September 2025 | 2025-10-13 | SYP26.3M | SYP1.3M | SYP2.6M | SYP22.3M | Approved | |
| Certificate 2August 2025 | 2025-08-30 | SYP23.5M | SYP1.2M | SYP2.4M | SYP20M | Approved | |
| Certificate 1June 2025 | 2025-07-16 | SYP14.3M | SYP712.5K | SYP1.4M | SYP12.1M | Approved |