Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦5⁩ — December 2025

e-Litigation platform Release 2 development

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
5
Date
⁦2026-01-11⁩
Reference
PAY-2025-010-05

Interim payment certificate no. (⁦5⁩)

For the work of December 2025

Contract number
PSA/2025/010
Tender file no.
2503810524
Contract
e-Litigation platform Release 2 development
Contractor
Integrated Digital Solutions Co.
Contractor tax number
TX-406274
Project
e-Litigation & Judicial Notification Platform — Release 2
Contract period
⁦2025-06-01⁩ — ⁦2026-11-30⁩
Original contract value
SYP370,000,000
Current contract value
SYP370,000,000
Linked milestone
Release 1 built · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date139,250,000
2Less: previous certificates(100,500,000)
3Value of work in this certificate38,750,000
4Less: retention (⁦5%⁩)(1,937,500)
5Less: advance payment recovery (⁦10%⁩)(3,875,000)
6Less: delay and breach penalties0
7Total deductions(5,812,500)
8Net amount payable to the contractorSYP32,937,500

Amount in words: Thirty-two million nine hundred thirty-seven thousand five hundred Syrian pounds only

Retention held up to this certificate: SYP 7M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design55,500,00023,175,0007,475,00030,650,000⁦55%⁩
Licences & platform74,000,00026,725,0009,475,00036,200,000⁦49%⁩
Build & configuration111,000,00029,725,00012,050,00041,775,000⁦38%⁩
Systems integration55,500,00011,575,0005,125,00016,700,000⁦30%⁩
Testing & acceptance37,000,0005,650,0002,700,0008,350,000⁦23%⁩
Training & run37,000,0003,650,0001,925,0005,575,000⁦15%⁩
Total370,000,000100,500,00038,750,000139,250,000⁦38%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Lama Salloum

Salloum⁦2026-01-11⁩

Supervising engineer

Hamza Al-Hussein

Al-Hussein⁦2026-01-13⁩

Project manager

Kinan Azzam

Azzam⁦2026-01-16⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-01-19⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-01-22⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-11⁩

    Lama Salloum

  2. Engineer verifies quantities⁦2026-01-13⁩

    Hamza Al-Hussein · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2026-01-16⁩

    Kinan Azzam · Senior Digital Delivery Consultant — National PMO

    Took 3 days

  4. Payment order prepared⁦2026-01-19⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-22⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneRelease 1 builtDone · ⁦2026-03-02⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-01-19⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderHamza Al-Hussein → Omar Al-Nahhas
  • The project manager does not approve the paymentKinan Azzam → Dr. Samer Al-Daqqar

Certificate history

22 January 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-01-22 13:00

19 January 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-01-19 13:00

16 January 2026

  1. Approval: Kinan Azzam signed “Project manager certifies”

    2026-01-16 13:00

13 January 2026

  1. Approval: Hamza Al-Hussein signed “Engineer verifies quantities”

    2026-01-13 13:00

11 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-11 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close