Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SYP 46.3M — if approved the value becomes SYP 1.3B
Total
Increase
Decrease
Original valueVO 1Current value
Where the money is now
66% of the current value paid
66%
Paid
SYP841.5M
of a current value of SYP 1.3B
Retention held(10% of each certificate)
SYP84.2M
Advance not yet recovered(of an advance of SYP 121.5M)
SYP37.4M
Value remaining
SYP433.5M
AI insight
The contract is heading past its end date
Go-live runs 42 days behind plan. The extension claim was assessed at 28 days and the pending variation (SYP 46.25M) adds 21 days; approving both moves the contract end beyond 31 March 2027.