Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦19⁩ — May 2026

Madinat al-Salam water network — rehabilitation works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
19
Date
⁦2026-06-06⁩
Reference
PAY-2024-022-19

Interim payment certificate no. (⁦19⁩)

For the work of May 2026

Contract number
PSA/2024/022
Tender file no.
2402550290
Contract
Madinat al-Salam water network — rehabilitation works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,400,000,000
Current contract value
SYP1,400,000,000
Linked milestone
Testing & commissioning · MS-G5 Final handover

Certificate summary (SYP)

1Total value of work completed to date1,260,000,000
2Less: previous certificates(1,231,000,000)
3Value of work in this certificate29,000,000
4Less: retention (⁦10%⁩)(2,900,000)
5Less: advance payment recovery (⁦10%⁩)(2,900,000)
6Less: delay and breach penalties0
7Total deductions(5,800,000)
8Net amount payable to the contractorSYP23,200,000

Amount in words: Twenty-three million two hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 126M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation98,000,00097,175,000825,00098,000,000⁦100%⁩
Earthworks & foundations252,000,000249,150,0002,850,000252,000,000⁦100%⁩
Concrete & structural works434,000,000425,175,0008,825,000434,000,000⁦100%⁩
Mechanical, electrical & plumbing336,000,000325,150,00010,850,000336,000,000⁦100%⁩
Finishes & external works210,000,000122,325,0005,075,000127,400,000⁦61%⁩
Testing & commissioning70,000,00012,025,000575,00012,600,000⁦18%⁩
Total1,400,000,0001,231,000,00029,000,0001,260,000,000⁦90%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2026-06-06⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-06-08⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-06-11⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-06-14⁩

Final approver

Rasha Al-Mudarres

Al-Mudarres⁦2026-06-17⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-06-06⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2026-06-08⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-06-11⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-06-14⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-06-17⁩

    Rasha Al-Mudarres · Director General, Finance & Contracts

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneTesting & commissioningDone · ⁦2026-09-03⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Rasha Al-Mudarres
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Rasha Al-Mudarres

Certificate history

17 June 2026

  1. Payment: Rasha Al-Mudarres signed “Final approval”

    2026-06-17 13:00

14 June 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-06-14 13:00

11 June 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-06-11 13:00

8 June 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-06-08 13:00

6 June 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-06-06 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close