Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦17⁩ — March 2026

Madinat al-Salam water network — rehabilitation works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
17
Date
⁦2026-04-08⁩
Reference
PAY-2024-022-17

Interim payment certificate no. (⁦17⁩)

For the work of March 2026

Contract number
PSA/2024/022
Tender file no.
2402550290
Contract
Madinat al-Salam water network — rehabilitation works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,400,000,000
Current contract value
SYP1,400,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date1,188,500,000
2Less: previous certificates(1,141,250,000)
3Value of work in this certificate47,250,000
4Less: retention (⁦10%⁩)(4,725,000)
5Less: advance payment recovery (⁦10%⁩)(4,725,000)
6Less: delay and breach penalties0
7Total deductions(9,450,000)
8Net amount payable to the contractorSYP37,800,000

Amount in words: Thirty-seven million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 118.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation98,000,00096,225,0001,775,00098,000,000⁦100%⁩
Earthworks & foundations252,000,000246,250,0005,750,000252,000,000⁦100%⁩
Concrete & structural works434,000,000418,000,00016,000,000434,000,000⁦100%⁩
Mechanical, electrical & plumbing336,000,000295,000,00017,400,000312,400,000⁦93%⁩
Finishes & external works210,000,00074,825,0005,400,00080,225,000⁦38%⁩
Testing & commissioning70,000,00010,950,000925,00011,875,000⁦17%⁩
Total1,400,000,0001,141,250,00047,250,0001,188,500,000⁦85%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2026-04-08⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-04-10⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-04-13⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-04-16⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-04-19⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-04-08⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2026-04-10⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-04-13⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-04-16⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-04-19⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedDone · ⁦2026-05-24⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone approved ⁦2026-08-24⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

19 April 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-04-19 13:00

16 April 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-04-16 13:00

13 April 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-04-13 13:00

10 April 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-04-10 13:00

8 April 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-04-08 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close