Interim payment certificate no. (17)
For the work of March 2026
- Contract number
- PSA/2024/022
- Tender file no.
- 2402550290
- Contract
- Madinat al-Salam water network — rehabilitation works
- Contractor
- Al-Shahbaa Construction & Rehabilitation Co.
- Contractor tax number
- TX-415685
- Project
- Madinat al-Salam Drinking-Water Network (Quneitra)
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- SYP1,400,000,000
- Current contract value
- SYP1,400,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,188,500,000 |
| 2 | Less: previous certificates | (1,141,250,000) |
| 3 | Value of work in this certificate | 47,250,000 |
| 4 | Less: retention (10%) | (4,725,000) |
| 5 | Less: advance payment recovery (10%) | (4,725,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (9,450,000) |
| 8 | Net amount payable to the contractor | SYP37,800,000 |
Amount in words: Thirty-seven million eight hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 118.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 98,000,000 | 96,225,000 | 1,775,000 | 98,000,000 | 100% |
| Earthworks & foundations | 252,000,000 | 246,250,000 | 5,750,000 | 252,000,000 | 100% |
| Concrete & structural works | 434,000,000 | 418,000,000 | 16,000,000 | 434,000,000 | 100% |
| Mechanical, electrical & plumbing | 336,000,000 | 295,000,000 | 17,400,000 | 312,400,000 | 93% |
| Finishes & external works | 210,000,000 | 74,825,000 | 5,400,000 | 80,225,000 | 38% |
| Testing & commissioning | 70,000,000 | 10,950,000 | 925,000 | 11,875,000 | 17% |
| Total | 1,400,000,000 | 1,141,250,000 | 47,250,000 | 1,188,500,000 | 85% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Karim Al-Ibrahim
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Maher Al-Hamawi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar