Certificate ⁦16⁩ — February 2026

Madinat al-Salam water network — rehabilitation works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
16
Date
⁦2026-03-09⁩
Reference
PAY-2024-022-16

Interim payment certificate no. (⁦16⁩)

For the work of February 2026

Contract number
PSA/2024/022
Tender file no.
2402550290
Contract
Madinat al-Salam water network — rehabilitation works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,400,000,000
Current contract value
SYP1,400,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date1,141,250,000
2Less: previous certificates(1,080,750,000)
3Value of work in this certificate60,500,000
4Less: retention (⁦10%⁩)(6,050,000)
5Less: advance payment recovery (⁦10%⁩)(6,050,000)
6Less: delay and breach penalties0
7Total deductions(12,100,000)
8Net amount payable to the contractorSYP48,400,000

Amount in words: Forty-eight million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 114.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation98,000,00095,350,0002,650,00098,000,000⁦100%⁩
Earthworks & foundations252,000,000243,725,0008,275,000252,000,000⁦100%⁩
Concrete & structural works434,000,000412,175,00021,825,000434,000,000⁦100%⁩
Mechanical, electrical & plumbing336,000,000249,000,00019,800,000268,800,000⁦80%⁩
Finishes & external works210,000,00070,225,0006,800,00077,025,000⁦37%⁩
Testing & commissioning70,000,00010,275,0001,150,00011,425,000⁦16%⁩
Total1,400,000,0001,080,750,00060,500,0001,141,250,000⁦82%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2026-03-09⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-03-11⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-03-14⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-03-17⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-03-20⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-09⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2026-03-11⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-03-14⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-03-17⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-20⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedDone · ⁦2026-05-24⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone approved ⁦2026-08-24⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

20 March 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-03-20 13:00

17 March 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-03-17 13:00

14 March 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-03-14 13:00

11 March 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-03-11 13:00

9 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-09 09:00