Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 15
- Date
- 2026-02-07
- Reference
- PAY-2024-022-15
Interim payment certificate no. (15)
For the work of January 2026
- Contract number
- PSA/2024/022
- Tender file no.
- 2402550290
- Contract
- Madinat al-Salam water network — rehabilitation works
- Contractor
- Al-Shahbaa Construction & Rehabilitation Co.
- Contractor tax number
- TX-415685
- Project
- Madinat al-Salam Drinking-Water Network (Quneitra)
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- SYP1,400,000,000
- Current contract value
- SYP1,400,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,080,750,000 |
| 2 | Less: previous certificates | (1,007,000,000) |
| 3 | Value of work in this certificate | 73,750,000 |
| 4 | Less: retention (10%) | (7,375,000) |
| 5 | Less: advance payment recovery (10%) | (7,375,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (14,750,000) |
| 8 | Net amount payable to the contractor | SYP59,000,000 |
Amount in words: Fifty-nine million Syrian pounds only
Retention held up to this certificate: SYP 108.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 98,000,000 | 94,175,000 | 3,825,000 | 98,000,000 | 100% |
| Earthworks & foundations | 252,000,000 | 240,400,000 | 11,600,000 | 252,000,000 | 100% |
| Concrete & structural works | 434,000,000 | 405,150,000 | 28,850,000 | 434,000,000 | 100% |
| Mechanical, electrical & plumbing | 336,000,000 | 193,000,000 | 20,000,000 | 213,000,000 | 63% |
| Finishes & external works | 210,000,000 | 64,850,000 | 8,100,000 | 72,950,000 | 35% |
| Testing & commissioning | 70,000,000 | 9,425,000 | 1,375,000 | 10,800,000 | 15% |
| Total | 1,400,000,000 | 1,007,000,000 | 73,750,000 | 1,080,750,000 | 77% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Karim Al-Ibrahim
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Maher Al-Hamawi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar