Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-029On track3PlanningWaterfallNot startedDelivered by:Ministry of Education

e-Learning Platform & Computer Labs for Raqqa Schools

Add to watchlist

Computer labs in 30 schools in Raqqa city and an e-learning platform with the national curriculum, plus teacher training.

Budget (BAC)

SYP 187.5M

Actual cost

SYP 7.5M

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 187.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
PSA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2026-03-25⁩
ApprovedDMD-2026-006e-Learning platform & computer labs for Raqqa schools

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-029
Project
e-Learning Platform & Computer Labs for Raqqa Schools
Portfolio
Planning, Statistics & Capability Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Abdulrahman Al-Kilani
Project manager
Mariam Al-Zoubi

1The resultAuto-filled

Priority score

66 of 100

Class

P2

60–74

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the development framework⁦20%⁩4.618.0
Development value⁦12%⁩4.410.2
Economic & social return⁦8%⁩3.24.4
Urgency⁦10%⁩3.66.5
Legal requirement⁦10%⁩1.41.0
Risk⁦7%⁩1.36.5
Complexity⁦6%⁩1.65.1
Resource requirement⁦5%⁩1.14.9
Impact on citizens & beneficiaries⁦14%⁩3.07.0
Sustainability impact⁦3%⁩1.80.6
Digital transformation impact⁦5%⁩2.21.5
Total⁦100%⁩—66

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2026-03-25⁩ 14:59
2Evaluation checked against the modelMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-03-29⁩ 12:33
3Portfolio manager reviewTechnical acceptanceDr. Reem Al-QabbaniPortfolio managerApproved—⁦2026-03-30⁩ 13:40
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2026-04-01⁩ 14:47

Signatures

Evaluation checked against the model

Mariam Al-Zoubi

Approved⁦2026-03-29⁩

Portfolio manager review

Dr. Reem Al-Qabbani

Approved⁦2026-03-30⁩

Class approved — Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2026-04-01⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2026-03-25⁩

  1. Methodology review

    Evaluation checked against the model

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-03-29⁩ at ⁦12:33⁩

  2. Technical acceptance

    Portfolio manager review

    Dr. Reem Al-Qabbani · Portfolio manager

    Approved · ⁦2026-03-30⁩ at ⁦13:40⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2026-04-01⁩ at ⁦14:47⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.