Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Settle the funding before the tender

LL-2026-026 · Finance & funding · High impact · Published

  1. 1ContextThe Baniyas pilot seawater desalination plant.
  2. 2What happenedThe project was put on hold because its allocation was not in the investment plan after the tender went out.
  3. 3ImpactProject on hold and SYP ⁦225M of commitments frozen⁩.

Recommendation

For co-funded or Development-Fund requests, attach an in-principle allocation approval before committee review.

Captured by
Eng. Rami Youssef
Date
2026-07-27
Applies to
Infrastructure · Construction · Consulting