Grid-connection approvals take 4–6 monthsFrom 20 MW Qalamoun Solar FieldThe electricity transmission & distribution establishment took five months to approve connecting phase one to the grid.Recommendation: Put the grid operator’s approval on the critical path of any energy or water-pumping request.Open the lesson
Settle the funding before the tenderFrom Baniyas Pilot Seawater Desalination PlantThe project was put on hold because its allocation was not in the investment plan after the tender went out.Recommendation: For co-funded or Development-Fund requests, attach an in-principle allocation approval before committee review.Open the lesson