DMD-2026-008

Modern irrigation for the Hauran plain

FeasibilityProposal
Electronic form
Priority score
62

Preliminary score from screening — confirmed after evaluation

Estimated cost
SYP 1.6B
Net present value
SYP 316.5M
Internal rate of return
⁦10.4%⁩
Payback period
⁦6.4⁩ years
Rank in the 2027 plan
#9

of ⁦9⁩ candidates

  1. Gate into «Submitted»DecisionGoDate18 June 2026DraftComplete
  2. Gate into «Initial review»DecisionGoDate25 July 2026SubmittedComplete
  3. Gate into «Feasibility»DecisionGoDate31 August 2026Initial reviewComplete
  4. Gate into «Evaluation»DecisionNot held yetFeasibilityCurrent stageCurrent stage
  5. Gate into «Committee review»DecisionNot held yet5EvaluationNot started
  6. Gate into «Approved»DecisionNot held yet6Committee reviewNot started
  7. Gate into «Prioritized»DecisionNot held yet7ApprovedNot started
  8. Gate into «Converted to project»DecisionNot held yet8PrioritizedNot started
  9. 9Converted to projectNot started

The request as filed

What the requester wrote on the intake form

Problem
Farming on the Hauran plain relies on flood irrigation from weak wells; half the water is wasted and wheat and vegetable yields fall year after year.
Current state
9,000 m³ per hectare a year, diesel pumps running 10 hours a day, and well levels falling two metres a year.
Objective
A modern drip and sprinkler network covering 12,000 hectares with solar pumping, cutting water use 45%.
Expected scope
Design, irrigation networks and tanks, solar pumping stations and farmer training, with the Ministry of Agriculture and Daraa Governorate.

Expected benefits

Savings

Pumping cost for farmers down 60%

Sustainability

Water use down 45% and diesel generators retired

Strategic link

The objectives it serves and how well it aligns

Strategic alignment · Excellent

Related lessons learned

From similar past projects — read them before evaluation

Grid-connection approvals take 4–6 months

From 20 MW Qalamoun Solar Field

The electricity transmission & distribution establishment took five months to approve connecting phase one to the grid.

Recommendation: Put the grid operator’s approval on the critical path of any energy or water-pumping request.

Open the lesson

Settle the funding before the tender

From Baniyas Pilot Seawater Desalination Plant

The project was put on hold because its allocation was not in the investment plan after the tender went out.

Recommendation: For co-funded or Development-Fund requests, attach an in-principle allocation approval before committee review.

Open the lesson