DMD-2026-012

Al-Ghab plain irrigation canals rehabilitation

RejectedProject request
Priority score
32

Score confirmed by the evaluation panel

Estimated cost
SYP 2.1B
Net present value
⁦−SYP 1.2B⁩
Internal rate of return
⁦-10.2%⁩
Payback period
—

No payback within the horizon

Rank in the 2027 plan
—
  1. Gate into «Submitted»DecisionGoDate7 July 2026DraftComplete
  2. Gate into «Initial review»DecisionGoDate20 July 2026SubmittedComplete
  3. Gate into «Feasibility»DecisionGoDate1 August 2026Initial reviewComplete
  4. Gate into «Evaluation»DecisionGoDate14 August 2026FeasibilityComplete
  5. Gate into «Committee review»DecisionGoDate26 August 2026EvaluationComplete
  6. Gate into «Approved»DecisionOn holdDate8 September 2026Committee reviewCurrent stageCurrent stage
  7. Gate into «Prioritized»DecisionNot held yet7ApprovedNot started
  8. Gate into «Converted to project»DecisionNot held yet8PrioritizedNot started
  9. 9Converted to projectNot started

The request as filed

What the requester wrote on the intake form

Problem
Al-Ghab plain irrigation canals are damaged and partly blocked, so the irrigated area and wheat and sugar-beet output have fallen.
Current state
40% of the main canals are out of service, and the irrigated area fell from 60,000 to 34,000 hectares.
Objective
Rehabilitate the main and branch canals and gates, fully funded from the investment plan.
Expected scope
Desilting and lining the canals, rehabilitating the gates and lift stations, and three years of maintenance.

Expected benefits

Savings

Irrigated area up 26,000 hectares

Strategic link

The objectives it serves and how well it aligns

Strategic alignment · Fair

Related lessons learned

From similar past projects — read them before evaluation

Settle the funding before the tender

From Baniyas Pilot Seawater Desalination Plant

The project was put on hold because its allocation was not in the investment plan after the tender went out.

Recommendation: For co-funded or Development-Fund requests, attach an in-principle allocation approval before committee review.

Open the lesson

Grid-connection approvals take 4–6 months

From 20 MW Qalamoun Solar Field

The electricity transmission & distribution establishment took five months to approve connecting phase one to the grid.

Recommendation: Put the grid operator’s approval on the critical path of any energy or water-pumping request.

Open the lesson