Settle the funding before the tenderFrom Baniyas Pilot Seawater Desalination PlantThe project was put on hold because its allocation was not in the investment plan after the tender went out.Recommendation: For co-funded or Development-Fund requests, attach an in-principle allocation approval before committee review.Open the lesson
Grid-connection approvals take 4–6 monthsFrom 20 MW Qalamoun Solar FieldThe electricity transmission & distribution establishment took five months to approve connecting phase one to the grid.Recommendation: Put the grid operator’s approval on the critical path of any energy or water-pumping request.Open the lesson