Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Survey the ground before the design freeze

LL-2026-006 · Design · Medium impact · Published

  1. 1ContextThe Sheikh Najjar industrial city rehabilitation in Aleppo.
  2. 2What happenedDigging found soft soil, groundwater, rubble and undocumented utility lines; the services building’s foundations were redesigned.
  3. 3Impact⁦An approved variation and a 5⁩-week delay.

Recommendation

Make a geotechnical, utility and rubble survey part of feasibility for any reconstruction on a damaged site.

Captured by
Eng. Youssef Shehabi
Date
2026-05-12
Applies to
Infrastructure · Construction

Where it was used (⁦5⁩)