Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Knowledge base

Procedures, guidelines, policies and best practices.

What are you looking for?

One search across ⁦17⁩ articles, ⁦21⁩ lessons, ⁦8⁩ templates and ⁦25⁩ documents

Try:

Shelves

Pick a shelf to see its articles, or go to templates and lessons.

PMO picks

What any project manager needs before starting.

AI insight

Three projects enter tendering this quarter

The Deir ez-Zor suspension bridge, the Baniyas pilot desalination plant and the unified government contact centre are close to tender; on similar projects, contractor capacity and the funding model failed most.

Confidence⁦81%⁩

Most read

Recently revised

Due for review

Before year end

My saved

Articles you saved for later

Nothing saved yet. Open any article and press «Save».

Cost estimates and contingency

KB-202 · Guidelines · 6 min read

Contingency rates by project type, and what must never hide inside them.

Owner: Huda Al-Dandal·Updated 2026-05-20·Review by 2026-11-20

Reference rates

  1. 1Digital: ⁦10–15%⁩
  2. 2Construction: ⁦12–20%⁩
  3. 3Rehabilitating facilities where service to citizens carries on: ⁦20%⁩

Estimate separately

Data cleansing and migration, utility diversion and land allocation and handover are separate lines, never contingency.