Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Check the contractor’s financial capacity before award

LL-2026-004 · Procurement · High impact · Published

  1. 1Context⁦The Aleppo 230 kV substations rehabilitation under a supply⁩, install and civil-works contract.
  2. 2What happenedThe contractor ran into financial distress in month nine and transformer supply slowed; an executive task force was formed.
  3. 3Impact⁦SPI fell to 0⁩.⁦71 and the project went critical⁩.

Recommendation

⁦Add liquidity and existing commitments to pre-qualification for every tender over SYP 1⁩.⁦25bn⁩.

Captured by
Eng. Maher Al-Hamawi
Date
2026-09-21
Applies to
Infrastructure · Construction