DMD-2026-004

Allouk water station rehabilitation

Committee reviewImprovement
Electronic formPriority evaluation
Priority score
71

Score confirmed by the evaluation panel

Estimated cost
SYP 195M
Net present value
SYP 136.5M
Internal rate of return
⁦28.6%⁩
Payback period
⁦2.9⁩ years
Rank in the 2027 plan
#6

of ⁦9⁩ candidates

  1. Gate into «Submitted»DecisionGoDate6 May 2026DraftComplete
  2. Gate into «Initial review»DecisionGoDate15 June 2026SubmittedComplete
  3. Gate into «Feasibility»DecisionGoDate26 July 2026Initial reviewComplete
  4. Gate into «Evaluation»DecisionGoDate4 September 2026FeasibilityComplete
  5. Gate into «Committee review»DecisionGoDate14 October 2026EvaluationComplete
  6. Gate into «Approved»DecisionNot held yetCommittee reviewCurrent stageCurrent stage
  7. Gate into «Prioritized»DecisionNot held yet7ApprovedNot started
  8. Gate into «Converted to project»DecisionNot held yet8PrioritizedNot started
  9. 9Converted to projectNot started

The request as filed

What the requester wrote on the intake form

Problem
The Allouk water station supplies Al-Hasakah city and its countryside with drinking water; it has run at low capacity for years because of pump failures and power cuts, so thousands of families rely on water tankers.
Current state
The station runs at 35% of its design capacity, supply averages 40 litres a person a day, and families spend up to 15% of their income on tanker water.
Objective
Rehabilitate the station, its pumps and the transmission line, with back-up solar power, to raise supply to 100 litres a person a day.
Expected scope
Replacing the pumps and control panels, rehabilitating the wells and the transmission line, a 4 MW solar system, and two years of operation and maintenance with the Al-Hasakah drinking-water establishment.

Expected benefits

Customer satisfaction

Supply up from 40 to 100 litres a person a day

Time & speed

Pumping 20 hours a day instead of 6

Savings

Families’ tanker spending down about 70%

Strategic link

The objectives it serves and how well it aligns

Strategic alignment · Good

Related lessons learned

From similar past projects — read them before evaluation

Grid-connection approvals take 4–6 months

From 20 MW Qalamoun Solar Field

The electricity transmission & distribution establishment took five months to approve connecting phase one to the grid.

Recommendation: Put the grid operator’s approval on the critical path of any energy or water-pumping request.

Open the lesson

Check the contractor’s financial capacity before award

From Aleppo 230 kV Substations Rehabilitation

The contractor ran into financial distress in month nine and transformer supply slowed; an executive task force was formed.

Recommendation: Add liquidity and existing commitments to pre-qualification for every tender over SYP 1.25bn.