Survey the ground before the design freezeFrom Sheikh Najjar Industrial City RehabilitationDigging found soft soil, groundwater, rubble and undocumented utility lines; the services building’s foundations were redesigned.Recommendation: Make a geotechnical, utility and rubble survey part of feasibility for any reconstruction on a damaged site.Open the lesson
Confirm the land before approving the projectFrom Al-Mayadin General HospitalThe project was approved before Deir ez-Zor Governorate allocated the land, and stopped after the design award.Recommendation: Do not pass a construction request to committee without a final land-allocation decision.Open the lesson