Interim payment certificate no. (13)
For the work of October 2026
- Contract number
- PSA/2025/019
- Tender file no.
- 2504440641
- Contract
- Ministry of Finance e-archiving system — supply & implementation
- Contractor
- Integrated Financial & Administrative Systems Co.
- Contractor tax number
- TX-440781
- Project
- Ministry of Finance e-Archiving
- Contract period
- 2025-02-16 — 2026-09-30
- Original contract value
- SYP290,000,000
- Current contract value
- SYP290,000,000
- Linked milestone
- Hypercare & handover · MS-G5 Final handover
Certificate summary (SYP)
| 1 | Total value of work completed to date | 261,000,000 |
| 2 | Less: previous certificates | (251,500,000) |
| 3 | Value of work in this certificate | 9,500,000 |
| 4 | Less: retention (10%) | (950,000) |
| 5 | Less: advance payment recovery (10%) | (950,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,900,000) |
| 8 | Net amount payable to the contractor | SYP7,600,000 |
Amount in words: Seven million six hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 26.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 43,500,000 | 42,875,000 | 625,000 | 43,500,000 | 100% |
| Licences & platform | 58,000,000 | 56,575,000 | 1,425,000 | 58,000,000 | 100% |
| Build & configuration | 87,000,000 | 83,550,000 | 3,450,000 | 87,000,000 | 100% |
| Systems integration | 43,500,000 | 41,325,000 | 2,175,000 | 43,500,000 | 100% |
| Testing & acceptance | 29,000,000 | 17,425,000 | 1,125,000 | 18,550,000 | 64% |
| Training & run | 29,000,000 | 9,750,000 | 700,000 | 10,450,000 | 36% |
| Total | 290,000,000 | 251,500,000 | 9,500,000 | 261,000,000 | 90% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Mona Khaddour
Supervising engineer
Hamza Al-Hussein
Project manager
Nour Al-Jabiri
Finance & contracts
Omar Al-Nahhas
Final approver
Rasha Al-Mudarres