Interim payment certificate no. (12)
For the work of August 2026
- Contract number
- PSA/2025/019
- Tender file no.
- 2504440641
- Contract
- Ministry of Finance e-archiving system — supply & implementation
- Contractor
- Integrated Financial & Administrative Systems Co.
- Contractor tax number
- TX-440781
- Project
- Ministry of Finance e-Archiving
- Contract period
- 2025-02-16 — 2026-09-30
- Original contract value
- SYP290,000,000
- Current contract value
- SYP290,000,000
- Linked milestone
- Hypercare & handover · MS-G5 Final handover
Certificate summary (SYP)
| 1 | Total value of work completed to date | 251,500,000 |
| 2 | Less: previous certificates | (237,000,000) |
| 3 | Value of work in this certificate | 14,500,000 |
| 4 | Less: retention (10%) | (1,450,000) |
| 5 | Less: advance payment recovery (10%) | (1,450,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,900,000) |
| 8 | Net amount payable to the contractor | SYP11,600,000 |
Amount in words: Eleven million six hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 25.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 43,500,000 | 42,375,000 | 1,125,000 | 43,500,000 | 100% |
| Licences & platform | 58,000,000 | 55,625,000 | 2,375,000 | 58,000,000 | 100% |
| Build & configuration | 87,000,000 | 81,475,000 | 5,525,000 | 87,000,000 | 100% |
| Systems integration | 43,500,000 | 34,875,000 | 2,975,000 | 37,850,000 | 87% |
| Testing & acceptance | 29,000,000 | 13,700,000 | 1,400,000 | 15,100,000 | 52% |
| Training & run | 29,000,000 | 8,950,000 | 1,100,000 | 10,050,000 | 35% |
| Total | 290,000,000 | 237,000,000 | 14,500,000 | 251,500,000 | 87% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Mona Khaddour
Supervising engineer
Hamza Al-Hussein
Project manager
Nour Al-Jabiri
Finance & contracts
Omar Al-Nahhas
Final approver
Rasha Al-Mudarres