Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦5⁩ — December 2025

Network & server equipment — backup data centre

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
5
Date
⁦2026-01-11⁩
Reference
PAY-2025-012-05

Interim payment certificate no. (⁦5⁩)

For the work of December 2025

Contract number
PSA/2025/012
Tender file no.
2503950550
Contract
Network & server equipment — backup data centre
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Government Backup Data Centre, Homs — Phase 2
Contract period
⁦2025-06-01⁩ — ⁦2026-11-30⁩
Original contract value
SYP950,000,000
Current contract value
SYP950,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date271,250,000
2Less: previous certificates(195,750,000)
3Value of work in this certificate75,500,000
4Less: retention (⁦5%⁩)(3,775,000)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(3,775,000)
8Net amount payable to the contractorSYP71,725,000

Amount in words: Seventy-one million seven hundred twenty-five thousand Syrian pounds only

Retention held up to this certificate: SYP 13.6M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation66,500,00032,650,00011,150,00043,800,000⁦66%⁩
Earthworks & foundations171,000,00050,525,00017,825,00068,350,000⁦40%⁩
Concrete & structural works294,500,00066,650,00025,850,00092,500,000⁦31%⁩
Mechanical, electrical & plumbing228,000,00031,700,00013,875,00045,575,000⁦20%⁩
Finishes & external works142,500,00012,450,0005,850,00018,300,000⁦13%⁩
Testing & commissioning47,500,0001,775,000950,0002,725,000⁦6%⁩
Total950,000,000195,750,00075,500,000271,250,000⁦29%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-01-11⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-01-13⁩

Project manager

Eng. George Haddad

Haddad⁦2026-01-16⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-01-19⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-01-22⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-11⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-01-13⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-01-16⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-01-19⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-22⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-03-29⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-10-26⁩1 evidence file

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

22 January 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-01-22 13:00

19 January 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-01-19 13:00

16 January 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-01-16 13:00

13 January 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-01-13 13:00

11 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-11 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close