Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 9
- Date
- 2026-07-09
- Reference
- PAY-2025-012-09
Interim payment certificate no. (9)
For the work of June 2026
- Contract number
- PSA/2025/012
- Tender file no.
- 2503950550
- Contract
- Network & server equipment — backup data centre
- Contractor
- Modern Networks Telecom Co.
- Contractor tax number
- TX-409411
- Project
- Government Backup Data Centre, Homs — Phase 2
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- SYP950,000,000
- Current contract value
- SYP950,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 539,500,000 |
| 2 | Less: previous certificates | (485,250,000) |
| 3 | Value of work in this certificate | 54,250,000 |
| 4 | Less: retention (5%) | (2,712,500) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,712,500) |
| 8 | Net amount payable to the contractor | SYP51,537,500 |
Amount in words: Fifty-one million five hundred thirty-seven thousand five hundred Syrian pounds only
Retention held up to this certificate: SYP 27M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 66,500,000 | 61,325,000 | 5,175,000 | 66,500,000 | 100% |
| Earthworks & foundations | 171,000,000 | 143,450,000 | 13,125,000 | 156,575,000 | 92% |
| Concrete & structural works | 294,500,000 | 165,300,000 | 18,675,000 | 183,975,000 | 62% |
| Mechanical, electrical & plumbing | 228,000,000 | 79,275,000 | 11,350,000 | 90,625,000 | 40% |
| Finishes & external works | 142,500,000 | 31,325,000 | 5,100,000 | 36,425,000 | 26% |
| Testing & commissioning | 47,500,000 | 4,575,000 | 825,000 | 5,400,000 | 11% |
| Total | 950,000,000 | 485,250,000 | 54,250,000 | 539,500,000 | 57% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ammar Al-Ahmad
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. George Haddad
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar