Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦10⁩ — August 2026

Network & server equipment — backup data centre

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
10
Date
⁦2026-08-22⁩
Reference
PAY-2025-012-10

Interim payment certificate no. (⁦10⁩)

For the work of August 2026

Contract number
PSA/2025/012
Tender file no.
2503950550
Contract
Network & server equipment — backup data centre
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Government Backup Data Centre, Homs — Phase 2
Contract period
⁦2025-06-01⁩ — ⁦2026-11-30⁩
Original contract value
SYP950,000,000
Current contract value
SYP950,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date586,000,000
2Less: previous certificates(539,500,000)
3Value of work in this certificate46,500,000
4Less: retention (⁦5%⁩)(2,325,000)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(2,325,000)
8Net amount payable to the contractorSYP44,175,000

Amount in words: Forty-four million one hundred seventy-five thousand Syrian pounds only

Retention held up to this certificate: SYP 29.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation66,500,00062,600,0003,900,00066,500,000⁦100%⁩
Earthworks & foundations171,000,000160,050,00010,950,000171,000,000⁦100%⁩
Concrete & structural works294,500,000188,275,00016,375,000204,650,000⁦69%⁩
Mechanical, electrical & plumbing228,000,00088,450,00010,000,00098,450,000⁦43%⁩
Finishes & external works142,500,00035,000,0004,550,00039,550,000⁦28%⁩
Testing & commissioning47,500,0005,125,000725,0005,850,000⁦12%⁩
Total950,000,000539,500,00046,500,000586,000,000⁦62%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-08-22⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-08-24⁩

Project manager

Eng. George Haddad

Haddad⁦2026-08-27⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-08-30⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-09-02⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-08-22⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-08-24⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-08-27⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-08-30⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-02⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-08-02⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

2 September 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-09-02 13:00

30 August 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-08-30 13:00

27 August 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-08-27 13:00

24 August 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-08-24 13:00

22 August 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-08-22 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close