Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 4
- Date
- 2025-11-27
- Reference
- PAY-2025-012-04
Interim payment certificate no. (4)
For the work of November 2025
- Contract number
- PSA/2025/012
- Tender file no.
- 2503950550
- Contract
- Network & server equipment — backup data centre
- Contractor
- Modern Networks Telecom Co.
- Contractor tax number
- TX-409411
- Project
- Government Backup Data Centre, Homs — Phase 2
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- SYP950,000,000
- Current contract value
- SYP950,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 195,750,000 |
| 2 | Less: previous certificates | (124,500,000) |
| 3 | Value of work in this certificate | 71,250,000 |
| 4 | Less: retention (5%) | (3,562,500) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (3,562,500) |
| 8 | Net amount payable to the contractor | SYP67,687,500 |
Amount in words: Sixty-seven million six hundred eighty-seven thousand five hundred Syrian pounds only
Retention held up to this certificate: SYP 9.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 66,500,000 | 20,775,000 | 10,850,000 | 31,625,000 | 48% |
| Earthworks & foundations | 171,000,000 | 32,125,000 | 17,200,000 | 49,325,000 | 29% |
| Concrete & structural works | 294,500,000 | 42,375,000 | 24,375,000 | 66,750,000 | 23% |
| Mechanical, electrical & plumbing | 228,000,000 | 20,150,000 | 12,725,000 | 32,875,000 | 14% |
| Finishes & external works | 142,500,000 | 7,925,000 | 5,300,000 | 13,225,000 | 9% |
| Testing & commissioning | 47,500,000 | 1,150,000 | 800,000 | 1,950,000 | 4% |
| Total | 950,000,000 | 124,500,000 | 71,250,000 | 195,750,000 | 21% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ammar Al-Ahmad
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. George Haddad
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar