Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦8⁩ — June 2025

Madinat al-Salam water network — rehabilitation works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
8
Date
⁦2025-07-14⁩
Reference
PAY-2024-022-08

Interim payment certificate no. (⁦8⁩)

For the work of June 2025

Contract number
PSA/2024/022
Tender file no.
2402550290
Contract
Madinat al-Salam water network — rehabilitation works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,400,000,000
Current contract value
SYP1,400,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date495,000,000
2Less: previous certificates(411,750,000)
3Value of work in this certificate83,250,000
4Less: retention (⁦10%⁩)(8,325,000)
5Less: advance payment recovery (⁦10%⁩)(8,325,000)
6Less: delay and breach penalties0
7Total deductions(16,650,000)
8Net amount payable to the contractorSYP66,600,000

Amount in words: Sixty-six million six hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 49.5M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation98,000,00067,975,00011,950,00079,925,000⁦82%⁩
Earthworks & foundations252,000,000105,500,00019,250,000124,750,000⁦50%⁩
Concrete & structural works434,000,000140,250,00028,550,000168,800,000⁦39%⁩
Mechanical, electrical & plumbing336,000,00067,450,00015,700,00083,150,000⁦25%⁩
Finishes & external works210,000,00026,700,0006,725,00033,425,000⁦16%⁩
Testing & commissioning70,000,0003,875,0001,075,0004,950,000⁦7%⁩
Total1,400,000,000411,750,00083,250,000495,000,000⁦35%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2025-07-14⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-07-16⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2025-07-19⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-07-22⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-07-25⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-07-14⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2025-07-16⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-07-19⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2025-07-22⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-07-25⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2025-12-08⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-02-11⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

25 July 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-07-25 13:00

22 July 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-07-22 13:00

19 July 2025

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2025-07-19 13:00

16 July 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-07-16 13:00

14 July 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-07-14 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close