Interim payment certificate no. (6)
For the work of January 2025
- Contract number
- PSA/2024/009
- Tender file no.
- 2401640121
- Contract
- Digital signature & document e-verification development
- Contractor
- Integrated Digital Solutions Co.
- Contractor tax number
- TX-406274
- Project
- Digital Signature & e-Verification of Government Documents — Phase 1
- Contract period
- 2024-05-05 — 2025-07-31
- Original contract value
- SYP172,500,000
- Current contract value
- SYP172,500,000
- Linked milestone
- Integration & UAT · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 108,250,000 |
| 2 | Less: previous certificates | (87,250,000) |
| 3 | Value of work in this certificate | 21,000,000 |
| 4 | Less: retention (5%) | (1,050,000) |
| 5 | Less: advance payment recovery (10%) | (2,100,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (3,150,000) |
| 8 | Net amount payable to the contractor | SYP17,850,000 |
Amount in words: Seventeen million eight hundred fifty thousand Syrian pounds only
Retention held up to this certificate: SYP 5.4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 25,875,000 | 20,425,000 | 3,375,000 | 23,800,000 | 92% |
| Licences & platform | 34,500,000 | 23,400,000 | 4,750,000 | 28,150,000 | 82% |
| Build & configuration | 51,750,000 | 25,675,000 | 6,800,000 | 32,475,000 | 63% |
| Systems integration | 25,875,000 | 9,925,000 | 3,075,000 | 13,000,000 | 50% |
| Testing & acceptance | 17,250,000 | 4,775,000 | 1,725,000 | 6,500,000 | 38% |
| Training & run | 17,250,000 | 3,050,000 | 1,275,000 | 4,325,000 | 25% |
| Total | 172,500,000 | 87,250,000 | 21,000,000 | 108,250,000 | 63% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Lama Salloum
Supervising engineer
Hamza Al-Hussein
Project manager
Kinan Azzam
Finance & contracts
Omar Al-Nahhas
Final approver
Rasha Al-Mudarres